Europaudvalget 2023-24
EUU Alm.del Bilag 395
Offentligt
2838050_0001.png
Modtaget den
:
29/02/2024
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
2838050_0002.png
- 1177368 -
JUDGMENT OF THE GENERAL COURT (First Chamber, Extended
Composition)
28 February 2024
*
(State aid – Public financing of the Fehmarn Belt fixed rail-road link – Aid
granted by Denmark to Femern – Decision declaring the aid compatible with the
internal market – Individual aid – Important project of common European
interest – Necessity of the aid – Proportionality – Weighing the beneficial effects
of the aid against its adverse effects on trading conditions and on the maintenance
of undistorted competition – Communication on the criteria for the analysis of the
compatibility with the internal market of State aid to promote the implementation
of important projects of common European interest)
In Case T-390/20,
Scandlines Danmark ApS,
established in Copenhagen (Denmark),
Scandlines Deutschland GmbH,
established in Hamburg (Germany),
represented by L. Sandberg-Mørch, lawyer,
applicants,
supported by
European Community Shipowners’ Associations (ECSA),
established in
Brussels (Belgium), represented by L. Sandberg-Mørch and M. Honoré, lawyers,
by
Danish Ferry Association,
established in Copenhagen, represented by
L. Sandberg-Mørch and M. Honoré, lawyers,
by
- 459 -
* Language of the case: English.
EN
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
Naturschutzbund Deutschland eV (NABU),
established in Stuttgart (Germany),
represented by T. Hohmuth and R. Weyland, lawyers,
by
Verband Deutscher Reeder eV,
established in Hamburg, represented by
L. Sandberg-Mørch and M. Honoré, lawyers,
by
Aktionsbündnis gegen eine feste Fehmarnbeltquerung eV,
established in
Fehmarn (Germany), represented by L. Sandberg-Mørch and W. Mecklenburg,
lawyers,
by
Föreningen Svensk Sjöfart (FSS),
established in Gothenburg (Sweden),
represented by L. Sandberg-Mørch and M. Honoré, lawyers,
by
Rederi AB Nordö-Link,
established in Malmö (Sweden), represented by
L. Sandberg-Mørch and P. Werner, lawyers,
and by
Trelleborg Hamn AB,
established in Trelleborg (Sweden), represented by
L. Sandberg-Mørch and I. Ioannidis, lawyers,
interveners,
v
European Commission,
represented by S. Noë, acting as Agent,
defendant,
supported by
Kingdom of Denmark,
represented by M. Søndahl Wolff, acting as Agent, and
by R. Holdgaard, lawyer,
intervener,
THE GENERAL COURT (First Chamber, Extended Composition),
composed of S. Papasavvas, President, D. Spielmann, M. Brkan (Rapporteur),
I. Gâlea and T. Tóth, Judges,
Registrar: P. Cullen, Administrator,
2
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
having regard to the written part of the procedure,
further to the hearing on 24 January 2023,
gives the following
Judgment
1
By their action based on Article 263 TFEU, the applicants, Scandlines Danmark
ApS and Scandlines Deutschland GmbH, seek annulment of Commission
Decision C(2020) 1683 final of 20 March 2020 on the State aid SA.39078 –
2019/C (ex 2014/N) which Denmark implemented for Femern A/S (OJ 2020
L 339, p. 1) (‘the contested decision’).
I.
Background to the dispute
The Fehmarn Belt Fixed Link project
A.
2
The Fehmarn Belt Fixed Link project between Denmark and Germany was
approved by the treaty between the Kingdom of Denmark and the Federal
Republic of Germany concerning the Fehmarn Belt fixed link signed on
3 September 2008 and ratified in 2009 (‘the Fehmarn Belt Treaty’).
The project consists of, on the one hand, a rail and road tunnel (‘the Fixed Link’),
and, on the other, road hinterland connections in Denmark (‘the road
connections’) and rail hinterland connections in Denmark (‘the rail connections’)
(together, ‘the rail and road hinterland connections’).
The Fixed Link takes the form of an immersed tunnel under the Baltic Sea
between Rødby on the island of Lolland in Denmark and Puttgarden in Germany;
it will be approximately 19 kilometres long and will consist of an electrified
railway line and a motorway. The rail connections will include the expansion and
upgrade of the existing rail link between Ringsted (Denmark) and Rødby,
covering approximately 120 kilometres, which is owned by Banedanmark, the
Danish State public rail infrastructure manager.
The project was preceded by a planning phase. The European Commission was
given notification of the financing of that phase, as regards the Fixed Link and the
rail and road hinterland connections. By its decision of 13 July 2009 in Case
N 157/09 – Financing of the planning phase of the Fehmarn Belt fixed link
referred to in the
Official Journal of the European Union
(OJ 2009 C 202, p. 2)
(‘the Planning Decision’), the Commission concluded, first, that the measures
relating to the financing of the planning of the project may not constitute State aid
in so far as Femern had acted as a public authority, and, second, that, even if those
measures were likely to benefit the future operator of the Fixed Link, they were in
3
4
5
3
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
any event compatible with the internal market. It therefore decided not to raise any
objections within the meaning of Article 4(2) and (3) of Council Regulation (EC)
No 659/1999 of 22 March 1999 laying down detailed rules for the application of
Article [93 EC] (OJ 1999 L 83, p. 1).
6
Following an update of the amounts which had been assessed initially, the total
costs for the planning and construction of the Fixed Link were estimated at
52.6 billion Danish kroner (DKK) (approximately EUR 7.1 billion) and the costs
related to the planning and construction of the upgrading of the road and rail
hinterland connections were estimated at DKK 9.5 billion (approximately
EUR 1.3 billion), giving an estimated total cost of DKK 62.1 billion
(approximately EUR 8.4 billion) for the project.
Pursuant to Article 6 of the Fehmarn Belt Treaty and the Lov nr 575 om anlæg og
drift af en fast forbindelse over Femern Bælt med tilhørende landanlæg i Danmark
(Law No 575 on the construction and operation of the Fehmarn Belt Fixed Link
and Danish hinterland connections) of 4 May 2015 (‘the 2015 Construction Law’),
two public undertakings were entrusted with the execution of the project.
The first, Femern, established in 2005, is responsible for the financing,
construction and operation of the Fixed Link. The second, Femern Landanlæg
A/S, established in 2009, was appointed to manage the construction and operation
of the Danish hinterland connections. Femern Landanlæg is a subsidiary of Sund
& Bælt Holding A/S, which is owned by the Danish State. Femern became a
subsidiary of Femern Landanlæg following the latter’s establishment.
The works relating to the construction of the Fixed Link are carried out by Femern
under construction contracts subject to public procurement procedures.
The construction of the necessary upgrading of the road connections is undertaken
by the Danish Highways Directorate on behalf of the Danish State, and is financed
by Femern Landanlæg. The road connections will be part of the general Danish
road infrastructure network, which is financed, operated and maintained by the
Danish Highways Directorate. The construction and operation of the rail
connections is carried out by Banedanmark on behalf of the Danish State and is
financed by Femern Landanlæg.
The project is financed by Femern and Femern Landanlæg through capital
injections, State-guaranteed loans and loans from the Danish authorities. As from
the entry into service of the Fixed Link, Femern will receive the charges paid by
users of the Fixed Link in order to discharge its debt and will pay dividends to
Femern Landanlæg which the latter will use to discharge its own debt. Femern
Landanlæg will also receive 80% of the fees paid by the railway operators for use
of the rail connections, charged by Banedanmark, as ownership of those
connections will be shared by it and Banedanmark.
7
8
9
10
11
4
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
B.
12
Events prior to the dispute
During 2014 and 2015, the Commission received five complaints, the first of
which was lodged on 5 June 2014, claiming that the Kingdom of Denmark had
granted unlawful State aid that was incompatible with the internal market to
Femern and Femern Landanlæg.
During that same period, the Commission’s departments sent several requests for
information to the Danish authorities, which replied and provided further
information on a number of occasions.
By letter of 22 December 2014, in accordance with Article 108(3) TFEU, the
Danish authorities notified the Commission of the financing model for the
Fehmarn Belt Fixed Link project.
On 23 July 2015, the Commission adopted Decision C(2015) 5023 final on State
aid SA.39078 (2014/N) (Denmark) for the financing of the Fehmarn Belt Fixed
Link project, referred to in the Official Journal of 2 October 2015 (OJ 2015 C 325,
p. 5; ‘the Construction Decision’), by which it decided not to raise objections to
the measures notified by the Danish authorities. In that decision, the Commission
had concluded, inter alia, that, even if the measures granted to Femern for the
planning, construction and operation of the Fixed Link did constitute State aid
within the meaning of Article 107(1) TFEU, they were compatible with the
internal market pursuant to Article 107(3)(b) TFEU. More specifically, the
Commission had taken the view that the measures granted to Femern were
compatible with Article 107(3)(b) TFEU and with its Communication of 20 June
2014 on the criteria for the analysis of the compatibility with the internal market
of State aid to promote the execution of important projects of common European
interest (OJ 2014 C 188, p. 4; ‘the IPCEI Communication’), as well as with its
Notice on the application of Articles [107] and [108 TFEU] to State aid in the
form of guarantees (OJ 2008 C 155, p. 10; ‘the Guarantee Notice’).
By judgments of 13 December 2018,
Scandlines Danmark and Scandlines
Deutschland
v
Commission
(T-630/15, not published, EU:T:2018:942), and of
13 December 2018,
Stena Line Scandinavia
v
Commission
(T-631/15, not
published, EU:T:2018:944), the Court partially annulled the Construction
Decision.
As regards the public financing granted to Femern for the planning, construction
and operation of the Fixed Link, the Court upheld the applicants’ actions, finding
that the Commission had failed to fulfil its obligation under Article 108(3) TFEU
to initiate the formal investigation procedure in light of the existence of serious
difficulties.
In particular, as regards the necessity of the aid, the Court found that, while it
could not be ruled out that, in principle, aid was necessary for the realisation of
such a large project, the Commission’s examination of the necessity of the aid in
the Construction Decision was, at the very least, insufficient and imprecise,
13
14
15
16
17
18
5
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
which, first, indicated that there were serious difficulties, which should have
prompted the Commission to initiate the formal investigation procedure, and
second, meant that it was not possible to examine whether the Commission had
made a manifest error of assessment.
19
In respect of the proportionality of the aid granted to Femern, as regards the
Commission’s analysis in the Construction Decision, the Court found, in
particular, that the calculation of the repayment period for the aid and the eligible
costs was at the very least insufficient and imprecise, or even contradictory, so the
serious difficulties encountered by the Commission should have prompted it to
initiate the formal investigation procedure.
The Court also held that the Commission had erred in law and had made a
manifest error of assessment, in so far as, contrary to what is provided for in
point 5.3 of the Guarantee Notice, the conditions for the mobilisation of the
guarantees were not determined when the guarantees were initially granted.
C.
21
Administrative procedure
20
Following the delivery of the judgments of 13 December 2018,
Scandlines
Danmark and Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), and of 13 December 2018,
Stena Line Scandinavia
v
Commission
(T-631/15, not published, EU:T:2018:944), upheld by the Court of
Justice by the judgment of 6 October 2021,
Scandlines Danmark and Scandlines
Deutschland
v
Commission
(C-174/19 P and C-175/19 P, EU:C:2021:801), the
Commission, by letter of 14 June 2019, informed the Danish authorities of its
decision to initiate the formal investigation procedure, laid down in Article 108(2)
TFEU, in respect of the measures granted to Femern for the financing of the Fixed
Link (‘the Opening Decision’). The Opening Decision was published in the
Official Journal of 5 July 2019 (OJ 2019 C 226, p. 5).
D.
Contested decision
22
23
On 20 March 2020, the Commission adopted the contested decision.
The contested decision covers the measures granted to Femern for the planning,
construction and operation of the Fixed Link. By contrast, unlike the Construction
Decision, the contested decision does not concern the measures granted to Femern
Landanlæg as regards the financing of the road and rail hinterland connections.
According to Article 2 of the contested decision, the measures consisting of
capital injections and a combination of State loans and State guarantees in favour
of Femern, which Denmark at least partially put into effect unlawfully, constitute
State aid within the meaning of Article 107(1) TFEU.
24
6
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
25
Following the modification of those measures, as set out in the revised notification
which followed the Opening Decision, those measures are compatible with the
internal market on the basis of Article 107(3)(b) TFEU.
E.
Forms of order sought
26
The applicants, supported by European Community Shipowners’ Associations
(ECSA), Danish Ferry Association (‘DFA’), Naturschutzbund Deutschland eV
(NABU), Rederi AB Nordö-Link, Trelleborg Hamn AB, Aktionsbündnis gegen
eine feste Fehmarnbeltquerung eV (‘Aktionsbündnis’), Föreningen Svensk Sjöfart
(FSS) and Verband Deutscher Reeder eV (‘VDR’), claim that the Court should:
annul the contested decision;
order the Commission to pay the costs.
27
The Commission, supported by the Kingdom of Denmark, contends that the Court
should:
II.
dismiss the action;
order the applicants to pay the costs.
Law
28
In support of their action, the applicants raise two pleas in law, alleging, first, that
the Commission incorrectly classified the measures at issue as one single ad hoc
aid and, second, infringement of Article 107(3)(b) TFEU.
A.
The first plea in law, alleging that the Commission incorrectly classified
the measures at issue as one single ad hoc aid
29
The applicants, supported by Trelleborg Hamn, VDR, Aktionsbündnis and
NABU, complain that the Commission failed to examine separately the
compatibility of each State loan and each State guarantee granted by the Danish
authorities on the basis of the Lov nr 285 om projektering af fast forbindelse over
Femern Bælt med tilhørende landanlæg i Danmark (Law No 285 on the planning
of the Fehmarn Belt Fixed Link and Danish hinterland connections) of 15 April
2009 (‘the 2009 Planning Law’), and subsequently on the basis of the 2015
Construction Law. In addition, the applicants consider that each grant of State
guarantees or State loans under the 2009 Planning Law or the 2015 Construction
Law constitutes one single ad hoc aid which should have been notified separately
to the Commission.
According to the applicants, Trelleborg Hamn, VDR, Aktionsbündnis and NABU,
it is only in case of an aid scheme that the Commission may carry out a brief
examination consisting of analysing the underlying framework on the basis of
30
7
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
which individual aid is granted. Otherwise, according to the applicants, the
cumulative effect of each of the grants could not be brought to light. Similarly, the
applicants and those interveners consider that the statutory right to finance the
entire costs of the planning and construction of the Fixed Link from the entry into
force of the 2015 Construction Law is irrelevant on the ground that neither
Council Regulation (EU) 2015/1589 of 13 July 2015 laying down detailed rules
for the application of Article 108 TFEU (OJ 2015 L 248, p. 9) nor the case-law
permits a distinction to be drawn according to the point at which individual grants
are made.
31
32
The Commission, supported by the Kingdom of Denmark, disputes those
arguments.
As a preliminary point, it should be noted, as the main parties submit, that the
measures granted to Femern do not fall within the concept of an ‘aid scheme’
within the meaning of Article 1(d) of Regulation 2015/1589.
It follows that, as is apparent from recital 247 of the contested decision, the
measures at issue in the present case are individual aid within the meaning of
Article 1(e) of Regulation 2015/1589.
In that regard, the parties disagree on what the concept of ‘individual aid’ covers
and disagree on the consequences which flow from that concept as regards the
Commission’s examination of the compatibility of the measures at issue with the
internal market and as regards the obligation to notify those measures.
In the present case, as is apparent from recital 259 of the contested decision, the
Commission found that Femern had been granted three successive individual aids
to carry out the Fixed Link project. The first individual aid took the form of a
capital injection when the company was set up in 2005. The second individual aid
consisted of a capital injection, State guarantees and State loans following the
entry into force, on 17 April 2009, of the 2009 Planning Law. The third individual
aid consisted of a combination of State loans and State guarantees granted
following the entry into force, on 6 May 2015, of the 2015 Construction Law.
According to the Commission, each State loan or each State guarantee granted to
Femern on the basis of the 2009 Planning Law and then on the basis of the 2015
Construction Law corresponds to a tranche released under an authorised measure
for the implementation of aid, so that it is not necessary to notify each of the
tranches for the purposes of a separate examination of its compatibility with the
internal market.
In that regard, it should be noted that, in the present case, the Commission’s
authorisation relates not only to all the financing granted to Femern until the
adoption, on 20 March 2020, of the contested decision, but also to the financing to
be granted after that date, within the limits laid down by that decision.
In the first place, it is necessary to ascertain whether, as the applicants, Trelleborg
Hamn, VDR, Aktionsbündnis and NABU submit, the Commission was wrong to
33
34
35
36
37
8
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
conclude, in recital 259 of the contested decision, that Femern received three
individual aids, within the meaning of Article 1(e) of Regulation 2015/1589, in
order to finance the planning and construction of the Fixed Link project.
38
In that regard, the applicants and the interveners referred to in paragraph 37 above
claim that each grant of a new State loan or of a new State guarantee constitutes
separate individual aid within the meaning of Article 1(e) of Regulation
2015/1589. Thus, between 2010 and 2019, Femern received no fewer than 15
individual aids within the meaning of that provision.
In the present case, in so far as the State loans and State guarantees granted to
Femern under the 2009 Planning Law and then under the 2015 Construction Law
are not granted through a single payment, but in successive tranches paid
according to the progress of the project, the Commission considered, in recital 248
of the contested decision, that it was necessary to determine whether Femern
received one or several individual aids linked to the 2009 Planning Law and the
2015 Construction Law or a series of individual aids granted each time a financial
transaction of Femern was implemented by the Danish authorities. In order to do
so, as is apparent from recitals 249 to 251 of the contested decision, the
Commission took the view that it was necessary to ascertain whether Femern had
obtained the legal right to receive individual aid under the 2009 Planning Law,
followed by another individual aid under the 2015 Construction Law.
In that regard, it should be noted that it cannot be excluded that several
consecutive measures of State intervention must, for the purposes of
Article 107(1) TFEU, be regarded as a single intervention. That could be the case
in particular where consecutive interventions, especially having regard to their
chronology, their purpose and the circumstances of the undertaking at the time of
those interventions, are so closely linked to each other that they are inseparable
from one another (judgment of 19 March 2013,
Bouygues and Others
v
Commission and Others,
C-399/10 P and C-401/10 P, EU:C:2013:175,
paragraphs 103 and 104). Furthermore, the fact that a measure is paid in
successive tranches does not change the nature of the aid as a single package (see,
to that effect, judgment of 6 October 1999,
Salomon
v
Commission,
T-123/97,
EU:T:1999:245, paragraph 75).
In the present case, it should be noted, first, that it is not disputed that the
financing provided for by the 2009 Planning Law was intended to enable Femern
to finance the planning costs of the Fixed Link project. Thus, the purpose of the
financing provided for by that law was to finance specific costs of a specific
project, namely those relating to the planning of the Fixed Link project, and were
therefore so closely linked to each other that they were inseparable from one
another. It follows that the Commission did not make an incorrect legal
classification in finding that all the financing granted on the basis of the 2009
Planning Law came under the same individual aid within the meaning of
Article 1(e) of Regulation 2015/1589, even if that aid had been paid in several
tranches.
39
40
41
9
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
42
Second, it is also not disputed that the State loans and State guarantees provided
for by the 2015 Construction Law are intended to enable Femern, as is apparent
from recital 251 of the contested decision, to refinance the planning costs and to
finance the construction costs of the Fixed Link. The purpose of those State loans
and those State guarantees, provided for in Section 4 of that law, is to finance
specific costs of a specific project, namely the costs of the construction of the
Fixed Link and the costs relating to the refinancing of the planning costs, and
therefore are so closely linked to each other that they are inseparable from one
another. It follows that the Commission also did not make an incorrect legal
classification in finding that the State loans and the State guarantees granted
pursuant to the 2015 Construction Law come under the same individual aid within
the meaning of Article 1(e) of Regulation 2015/1589, even if that aid is paid in
several tranches, including after the adoption of the contested decision.
The considerations set out in paragraphs 41 and 42 above are not called into
question by the argument that, in essence, Femern does not have a legal right to
receive aid on the basis of the 2009 Planning Law or the 2015 Construction Law
on the ground that the Danish authorities have, for the grant of funding, a
discretion which is not limited to a technical application. It must be noted that that
argument is based on the relevant criteria for the identification of an aid scheme
within the meaning of Article 1(d) of Regulation 2015/1589.
As noted in paragraph 39 above, for the purposes of identifying individual aid
within the meaning of Article 1(e) of Regulation 2015/1589, the Commission did
not use the concept of an ‘aid scheme’ within the meaning of Article 1(d) of that
regulation, but relied on the criterion of the beneficiary’s legal right to receive aid
under the national legislation.
In that regard, it must be noted that, according to the case-law, State aid must be
regarded as being ‘granted’, within the meaning of Article 107(1) TFEU, on the
date on which the right to receive it is conferred on the beneficiary under the
applicable national legislation (see judgment of 25 January 2022,
Commission
v
European Food and Others,
C-638/19 P, EU:C:2022:50, paragraph 115 and the
case-law cited).
In the present case, it is apparent from recitals 251 to 256 of the contested decision
that, on the basis of the wording of Section 4 of the 2015 Construction Law,
which is drafted in terms that are similar to those of Section 7 of the 2009
Planning Law, the explanations provided by the Danish authorities and the
preparatory notes relating to the 2015 Construction Law, the Commission
considered that the Danish Minister for Finance had a limited discretion which
was not capable of calling into question Femern’s legal right to receive the State
loans and State guarantees granted to it under those laws. Thus, in recital 257 of
the contested decision, the Commission concluded that Femern had obtained the
legal right to finance the planning and construction of the Fixed Link from the
entry into force of the 2015 Construction Law, with the result that that entity was
granted individual aid. It must be noted that, even though it is not expressly stated
43
44
45
46
10
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
in recital 257 of the contested decision, the Commission implicitly reached the
same conclusion as regards the 2009 Planning Law. The Commission reasoned by
analogy, which has not been challenged by the applicants, between the 2015
Construction Law and the 2009 Planning Law, with the result that the conclusion
reached in respect of the former can be extended to the latter.
47
It is true that, as the applicants, Trelleborg Hamn, VDR, Aktionsbündnis and
NABU state, in the context of the implementation of the State guarantees and
State loans which Femern received under the 2015 Construction Law and the 2009
Planning Law, the Danish Minister for Finance has discretion to define guidelines
and to issue binding directives on how Femern is to obtain the loans, the
instruments that are necessary and the requirements to be imposed. Furthermore, it
is also true that, in certain specific circumstances, the Danmarks nationalbank
(National Bank of Denmark) might not grant a loan application.
It must be stated, however, that the applicants, Trelleborg Hamn, VDR,
Aktionsbündnis and NABU have not in any way substantiated the reasons why it
must be inferred that the Danish Minister for Finance or the National Bank of
Denmark could call into question, as such, the legal right to receive State loans or
State guarantees.
In that regard, it must be noted that, as is apparent from recitals 253 and 254 of the
contested decision, the discretion of the Danish Minister for Finance is limited and
concerns only practical and technical conditions and rules intended to ensure the
sound management of public resources. The same finding must be made as
regards the role of the National Bank of Denmark in granting financing to Femern.
The grounds for a refusal to grant such financing are limited and also concern the
sound management of public resources. The exercise of powers intended to ensure
the proper management of public resources cannot call into question, as such,
Femern’s right to receive the State loans and the State guarantees granted to it by
the Danish Parliament.
The argument put forward by Trelleborg Hamn, VDR, Aktionsbündnis and
NABU that, in essence, the 2015 Construction Law cannot constitute the basis for
Femern’s legal right to receive aid on the ground that, as regards the grant of
financing, the conditions laid down by that law and by the Construction Decision
differ from those laid down in the contested decision cannot succeed. Contrary to
what is claimed by those interveners, it must be noted that, as regards Femern’s
financing, Section 4 of the 2015 Construction Law provides for that entity’s right
to receive State loans and State guarantees for the refinancing of the planning and
for the financing of the construction and operation of the Fixed Link. By contrast,
that law does not lay down limits or conditions governing the payment of the
various tranches of the aid, which were set out in the alternative financing model
provided by the Danish authorities during the formal investigation procedure in
the context of which it was provided, inter alia, that the State loans and the State
guarantees may not be used to cover the operating costs of the Fixed Link. It must
be held that the fact that the limits laid down in the Construction Decision differ
48
49
50
11
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
from those set out in the contested decision at the end of the formal investigation
procedure is irrelevant for calling into question whether Femern has a legal right
to receive aid. A distinction must be drawn between, on the one hand, the
recipient’s legal right to receive aid for a specific project resulting from a
commitment by the national authorities and, on the other hand, the limits or
conditions which govern the implementation of that aid and which are capable of
being defined or adjusted in the light of any observations made by the
Commission during the formal investigation procedure.
51
Accordingly, the Commission did not make an error of assessment in concluding,
in recital 259 of the contested decision, that Femern had obtained three separate
individual aids, namely a first individual aid granted in 2005, a second individual
aid granted in 2009 with the adoption of the 2009 Planning Law and a third
individual aid granted in 2015 with the adoption of the 2015 Construction Law.
In the second place, it is necessary to ascertain whether the Commission made an
error of assessment in examining jointly the compatibility of the three individual
aids identified in recital 259 of the contested decision.
In the present case, as regards the capital injections, the Commission assessed
them, in recital 377 of the contested decision, at DKK 510 million
(EUR 68.4 million). As regards the combination of State loans and State
guarantees, it is apparent from recital 348 of the contested decision that, in
accordance with the alternative financing model provided by the Danish
authorities during the formal investigation procedure, Femern cannot receive State
loans and guarantees which, taken together, would exceed a maximum guaranteed
amount of DKK 69.3 billion (EUR 9.3 billion), and, in recital 349 of the contested
decision, that Femern will have to have terminated all loans with a State guarantee
and have repaid all State loans at the latest 16 years after the start of operation of
the link.
It should be noted that it is not disputed that the three individual aids identified by
the Commission in recital 259 of the contested decision were granted to Femern in
order to finance the planning and construction of the Fixed Link. Consequently,
since those three individual aids granted to Femern are intended to finance the
planning and construction of one and the same project, the Commission could
legitimately examine the compatibility of those aids with the internal market by
taking into account all the financing that that entity might receive in order to
finance the planning and construction of the Fixed Link project.
Contrary to what the applicants submit, a joint examination of all the financing
that may be granted to Femern on the basis of the individual aids identified in
recital 259 of the contested decision does not prevent the cumulative effect of
those aids from being taken into account. On the contrary, in order to assess the
cumulative effect of the financing granted by a Member State to an undertaking in
order to carry out a particular project, it is precisely by taking into account all the
financing classified as State aid within the meaning of Article 107(1) TFEU that
52
53
54
55
12
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
the Commission is in a position to assess the effect of that financing on
competition in the context of the examination of one of the derogations provided
for in Article 107(3) TFEU. That is all the more so in a situation such as that in
the present case, where what is at issue is an investment in a transport
infrastructure considered to be an important project of common European interest
within the meaning of Article 107(3)(b) TFEU, the implementation of which
involves the payment of public financing over a long period.
56
For a project on a scale such as that of the Fixed Link, a joint examination of all
the financing which Femern might receive in order to carry out the project is the
only way of assessing the compatibility of the aid with the internal market in the
light of the criteria set out in the IPCEI Communication. In particular, as will be
examined in the context of the second complaint in the third part of the second
plea, in accordance with paragraph 31 of the IPCEI Communication, the
maximum level of aid granted for a project is defined by reference to the
identified funding gap in relation to the eligible costs. In that regard, as is apparent
from recitals 166 and 320 of the contested decision, in the alternative financing
model submitted during the formal investigation procedure, the Danish authorities
included in the eligible costs of the project not only the construction costs but also
the planning costs of the Fixed Link.
Thus, since it was necessary for the Commission to examine the compatibility of
all the financing which Femern may receive for the Fixed Link project, it is
necessary to reject the arguments of the applicants, Trelleborg Hamn, VDR,
Aktionsbündnis and NABU, whereby they claim, in essence, that the Commission
infringed Article 1(e) of Regulation 2015/1589 in that, on that ground, it carried
out a brief examination of the individual aids granted to Femern.
As regards the argument of Trelleborg Hamn, VDR, Aktionsbündnis and NABU
that, in essence, since the delivery of the judgment of 19 September 2018,
HH
Ferries and Others
v
Commission
(T-68/15, EU:T:2018:563), the Commission is
required to carry out a separate examination of each State loan and each State
guarantee in favour of Femern, it must be held that that judgment cannot be
interpreted as requiring the Commission to carry out such a separate examination
of each financing granted to that entity. In that judgment, the Court had found
only that the Commission experienced, during the preliminary examination phase
in respect of the measures at issue in the case which led to that judgment, serious
difficulties with respect to the classification of the State guarantees as an aid
scheme, finding, inter alia, an error in so far as it had been found that those
guarantees were not linked to a specific project within the meaning of Article 1(d)
of Regulation No 659/1999 (paragraph 80 of that judgment). However, it cannot
be inferred, from that, that there is any general obligation on the Commission to
examine separately each State guarantee granted to the same beneficiary for the
same project. It follows that the Commission cannot be criticised for not having
verified, for each of the 15 loans relied on by the applicants in their reply, the
criterion that the application for aid must be made prior to the start of the work for
the purposes of determining the incentive effect of the aid.
57
58
13
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
59
The argument of the applicants, Trelleborg Hamn, VDR, Aktionsbündnis and
NABU that, in essence, the joint examination of the compatibility of all the
financing granted to Femern is contrary to decision-making practice cannot
succeed. According to settled case-law, the Commission’s decision-making
practice in other cases cannot affect the validity of a contested decision, which can
be assessed only in the light of the objective rules of the Treaty (judgments of
20 May 2010,
Todaro Nunziatina & C.,
C-138/09, EU:C:2010:291, paragraph 21,
and of 24 September 2019,
Fortischem
v
Commission,
T-121/15, EU:T:2019:684,
paragraph 249).
Nor can the Court accept the argument that the Commission did not clearly define
the amount of authorised aid. In recital 350 of the contested decision, the
Commission concluded that the aid amount was DKK 12.046 billion
(EUR 1.615 billion), which includes capital injections and the State aid associated
with State-guaranteed loans and State loans, and that, first, the calculation of the
aid amount in the alternative model is based on an increase of the premium from
0.15% to 2% and, second, for loans already taken up, the aid alternative funding
gap calculation model takes into account that the premium was limited to 0.15%.
Accordingly, the arguments alleging that the Commission made an error of
assessment by jointly examining the three individual aids granted to Femern to
finance the planning and construction of the Fixed Link must be rejected as
unfounded.
In the third place, it is necessary to reject the line of argument that, in essence,
each State loan and each State guarantee granted to Femern under the 2009
Planning Law and the 2015 Construction Law should have been notified
separately by the Danish authorities.
As follows from paragraphs 41 and 42 above, the Commission was entitled to
consider, first, that all the financing granted under the 2009 Planning Law
constituted individual aid within the meaning of Article 1(e) of Regulation
2015/1589 and, second, that all the State loans and State guarantees which Femern
may receive under the 2015 Construction Law also fall within the scope of
individual aid within the meaning of that provision. Thus, since each grant of a
State loan or a State guarantee does not constitute, contrary to what the applicants,
Trelleborg Hamn, VDR, Aktionsbündnis and NABU claim, new separate
individual aid, the Commission was not under an obligation to require the Danish
authorities to notify it of each financial transaction carried out in favour of Femern
on the basis of the 2009 Planning Law and then the 2015 Construction Law.
Furthermore, as regards the State loans and State guarantees granted to Femern on
the basis of the 2015 Construction Law after the adoption of the contested
decision, only those which exceed the limits laid down in the contested decision
should be notified to the Commission, in so far as they are not covered by the
declaration of compatibility of the contested decision (see, to that effect and by
60
61
62
63
64
14
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
analogy, judgment of 12 July 2018,
Austria
v
Commission,
T-356/15,
EU:T:2018:439, paragraph 266).
65
In the fourth place, as regards the alleged infringement, relied on by the
applicants, of Article 107(1) TFEU resulting from an infringement of Regulation
2015/1589, it is sufficient to note that the applicants are wrong to claim that that
regulation was adopted in order to implement Article 107 TFEU. That regulation
does not concern the substantive provisions relating to State aid, laid down in
Article 107 TFEU, but concerns the detailed rules for the application of the
provisions relating to the procedure for reviewing such aid, laid down in
Article 108 TFEU. Accordingly, the alleged infringement of Article 107(1) TFEU,
relied on by the applicants, must be rejected.
Lastly, by an argument set out for the first time in their reply, the applicants
submit, in essence, that the Commission cannot consider, on the one hand, that all
the State guarantees and State loans were granted following the entry into force of
the 2015 Construction Law and, on the other hand, that only two of the loans
granted by the Danish authorities on the basis of that law were regarded as
unlawful aid. It must be stated that the application does not contain any complaint
challenging the findings and conclusions as to the lawfulness of the aid. In
addition, the applicants have not explained why all the aid that may be paid on the
basis of the 2015 Construction Law should be regarded as unlawful, with the
result that their arguments must be rejected as being insufficiently substantiated.
In any event, the question of whether part of the financing was paid prematurely
in breach of Article 108(3) TFEU has no bearing on whether the 2015
Construction Law grants Femern a legal right to receive aid.
It follows from the foregoing considerations that the first plea in law must be
rejected in its entirety.
B.
68
The second plea in law, alleging infringement of Article 107(3)(b) TFEU
66
67
The second plea consists, in essence, of four parts, first, alleging that the
Commission incorrectly classified the project as a project of common European
interest, second, alleging that the Commission wrongly concluded that the aid was
necessary, third, alleging that the Commission wrongly concluded that the aid was
proportionate and, fourth, challenging the analysis of the avoidance of undue
distortions of competition and the balancing test.
As a preliminary point, it must be noted that the application of Article 107(3)(b)
TFEU confers on the Commission a discretion, the exercise of which involves
economic and social assessments. It follows that a judicial review of the manner in
which that discretion is exercised is confined to establishing that the rules of
procedure and the rules relating to the duty to give reasons have been complied
with and to verifying the accuracy of the facts relied on and that there has been no
error of law, manifest error in the assessment of the facts or misuse of powers
(see, to that effect, judgments of 22 December 2008,
Régie Networks,
C-333/07,
69
15
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
EU:C:2008:764, paragraph 78, and of 13 December 2018,
Scandlines Danmark
and Scandlines Deutschland
v
Commission,
T-630/15, not published,
EU:T:2018:942, paragraph 141).
70
As regards the assessment by the EU Courts as to whether there is a manifest error
of assessment, it must be stated that, in order to establish that the Commission
made a manifest error in assessing complex facts such as to justify the annulment
of the contested act, the evidence adduced by the applicant must be sufficient to
make the factual assessments made in the act implausible (see, to that effect,
judgments of 12 December 1996,
AIUFFASS and AKT
v
Commission,
T-380/94,
EU:T:1996:195, paragraph 59, and of 19 September 2019,
FIH Holding and FIH
v
Commission,
T-386/14 RENV, not published, EU:T:2019:623, paragraph 69).
It is in the light of those preliminary considerations that the four parts of the
second plea must be examined.
1.
72
The first part, alleging that the Commission incorrectly classified the
project as a project of common European interest
71
By the first part of the second plea, the applicants, supported by NABU,
Aktionsbündnis, ECSA and Rederi Nordö-Link, put forward three complaints to
challenge the classification as a project of common European interest. The first
complaint alleges that studies carried out by the consultancy firm Incentive on
behalf of the Danish Government (‘the Incentive studies’) do not reveal a positive
socioeconomic return, the second alleges that the Commission relied on outdated
and inconsistent data in order to establish a positive socioeconomic return, and the
third alleges that the project is not co-financed by the beneficiary.
Furthermore, at the hearing, NABU raised for the first time a complaint alleging
breach of the principle of the phasing out of environmentally harmful subsidies
laid down in paragraph 19 of the IPCEI Communication.
Before examining the first two complaints, which it is appropriate to deal with
together, the Court considers it appropriate initially to rule, first, on the
admissibility of the new complaint raised by NABU at the hearing and, second, on
the merits of the third complaint alleging that the project is not co-financed by
Femern.
(a)
Admissibility of the new complaint alleging breach of the principle of the
phasing out of environmentally harmful subsidies
73
74
75
As regards the complaint raised for the first time at the hearing by NABU and
described in paragraph 73 above, it should be noted that, according to settled case-
law, first, although the fourth paragraph of Article 40 of the Statute of the Court of
Justice of the European Union, which applies to the General Court by virtue of
Article 53 of that statute, and Article 142(3) of the Rules of Procedure of the
General Court do not preclude an intervener from using arguments different from
16
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
those used by the party it is supporting, that is nevertheless on condition that they
do not alter the framework of the dispute and that the intervention is still intended
to support the form of order sought by that party (judgments of 8 June 1995,
Siemens
v
Commission,
T-459/93, EU:T:1995:100, paragraph 21, and of
29 November 2016,
T & L Sugars and Sidul Açúcares
v
Commission,
T-279/11,
not published, EU:T:2016:683, paragraph 31).
76
Second, in accordance with Article 84(1) of the Rules of Procedure, no new plea
in law may be introduced in the course of proceedings unless it is based on
matters of law or fact which have come to light in the course of the procedure.
However, a plea which constitutes an amplification of a plea previously made,
either expressly or by implication, in the original application and is closely linked
to it must be declared admissible. The same applies to a complaint made in
support of a plea in law. To be regarded as an amplification of a plea or a head of
claim previously advanced, a new line of argumentation must, in relation to the
pleas or heads of claim initially set out in the application, present a sufficiently
close connection with the pleas or heads of claim initially put forward in order to
be considered as forming part of the normal evolution of debate in proceedings
before the Court (see, to that effect, judgments of 16 November 2011,
Groupe
Gascogne
v
Commission,
T-72/06, not published, EU:T:2011:671, paragraphs 23
and 27; of 22 April 2016,
Italy and Eurallumina
v
Commission,
T-60/06 RENV II
and T-62/06 RENV II, EU:T:2016:233, paragraphs 45 and 46; and of
20 November 2017,
Petrov and Others
v
Parliament,
T-452/15, EU:T:2017:822,
paragraph 46).
It must be stated that the application does not contain any complaint or argument
seeking to claim, expressly or by implication, that the criterion laid down in
paragraph 19 of the IPCEI Communication is not satisfied.
Thus, even if, as NABU argued at the hearing, the arguments set out in its
statement in intervention in order to challenge the necessity of the aid, alleging
that the Fixed Link would have harmful effects on the environment, were
intended, in essence, to argue that the grant of aid to Femern contravenes the
principle of the phasing out of environmentally harmful subsidies laid down in
paragraph 19 of the IPCEI Communication, it must be held that those arguments
support a complaint which was not raised in the application and must therefore be
rejected as inadmissible.
In any event, it must be held that those arguments are not supported by any
evidence, with the result that that new complaint must, in any case, be rejected.
(b)
80
The third complaint, alleging that the project is not co-financed by
Femern
77
78
79
The applicants, NABU, Aktionsbündnis and ECSA submit that, by taking the
view that the project is financed by Femern with future revenues from the fees
collected from the users of the Fixed Link, the Commission disregarded the
17
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
requirement, laid down in paragraph 18 of the IPCEI Communication, that the
project be co-financed by the beneficiary of the aid. According to the applicants,
the co-financing requirement requires that the beneficiary of the aid make an
upfront contribution to the project so that it assumes a share of the risk.
81
82
The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
It should be noted that paragraph 18 of the IPCEI Communication requires that
the project include co-financing by the beneficiary. In that regard, it must be held
that that condition is satisfied, in particular where, as in the present case, the
project is funded in large part by the beneficiaries of the measures, on account of
the fact that tolls and fees will be charged to users of the fixed link (see, to that
effect, judgment of 13 December 2018,
Scandlines Danmark and Scandlines
Deutschland
v
Commission,
T-630/15, not published, EU:T:2018:942,
paragraph 180).
Contrary to what is claimed by the applicants, NABU, Aktionsbündnis and ECSA,
the co-financing requirement laid down in paragraph 18 of the IPCEI
Communication cannot be interpreted as requiring the beneficiary of the aid
necessarily to contribute upfront to the financing of the project. Unlike the
conditions governing the contribution by beneficiaries of restructuring aid, laid
down in points 62 to 64 of the Guidelines on State aid for rescuing and
restructuring non-financial undertakings in difficulty (OJ 2014 C 249, p. 1), the
requirement for co-financing of the project by the beneficiary of the aid, set out in
paragraph 18 of the IPCEI Communication, is not accompanied by any particular
condition. In that regard, as the Commission is fully entitled to submit, it must be
stated that the conditions governing the contribution by beneficiaries of
restructuring aid differ from the co-financing requirement laid down in the IPCEI
Communication.
Therefore, Femern cannot be required to contribute upfront to the financing of the
project. It follows that, by finding in recital 278 of the contested decision that the
project at issue is co-financed by the beneficiary of the aid, the Commission did
not disregard the requirement that the project be co-financed by the beneficiary of
the aid, laid down in paragraph 18 of the IPCEI Communication.
Accordingly, the complaint alleging that the project is not co-financed by Femern
must be rejected as unfounded.
(c)
86
The first and second complaints, alleging that there is no positive
socioeconomic return
83
84
85
In the first place, as regards the first complaint alleging that there is no positive
socioeconomic return, the applicants, NABU, Aktionsbündnis, ECSA and Rederi
Nordö-Link submit that the Commission made manifest errors of assessment in
18
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
the examination of the socioeconomic return of the Fixed Link on the basis of the
Incentive studies.
87
In the second place, by their second complaint, the applicants, NABU,
Aktionsbündnis, ECSA and Rederi Nordö-Link submit that the Commission made
a manifest error of assessment on the ground that, in order to find that there was a
positive socioeconomic return, it relied on data which were outdated and
inconsistent with those used in the context of the analysis of the proportionality of
the aid in order to calculate the funding gap.
The Commission contends that the findings in the contested decision which are
not disputed by the applicants are sufficient to establish that the Fixed Link
project can be regarded as a project of common European interest in accordance
with the criteria laid down in the IPCEI Communication, with the result that the
first and second complaints are ineffective.
In that regard, it should be noted that, by their first and second complaints, the
applicants, supported by NABU, Aktionsbündnis, ECSA and Rederi Nordö-Link,
submit, first, that the Fixed Link project does not offer a positive socioeconomic
return and, second, that the data used to calculate that return are outdated and
inconsistent with the data used to examine the proportionality of the aid. Thus, by
those two complaints, the applicants merely dispute the Commission’s findings in
recitals 275 to 277 of the contested decision.
It is necessary to ascertain whether, as the Commission submits, the first and
second complaints are ineffective on the ground that it was entitled to consider
that the Fixed Link project constituted a project of common European interest
without relying on the results of the Incentive studies.
In that regard, it must be noted that the concept of ‘common European interest’
laid down in Article 107(3)(b) TFEU must be interpreted strictly and that a project
may be so classified only if it forms part of a transnational European programme
jointly supported by a number of Member State governments or arises from
concerted action by a number of Member States to combat a common threat (see,
to that effect, judgments of 6 October 2009,
Germany
v
Commission,
T-21/06, not
published, EU:T:2009:387, paragraph 70, and of 13 December 2018,
Scandlines
Danmark and Scandlines Deutschland
v
Commission,
T-630/15, not published,
EU:T:2018:942, paragraph 170).
The concept of ‘common European interest’ was clarified in the IPCEI
Communication. In particular, first of all, paragraph 3.2.1 of that communication
sets out ‘general cumulative criteria’ to be satisfied in order for a project to fall
within the derogation provided for in Article 107(3)(b) TFEU. According to
paragraph 14 of the IPCEI Communication, the project must contribute ‘in a
concrete, clear and identifiable manner to one or more Union objectives and must
have a significant impact on competitiveness of the Union, sustainable growth,
addressing societal challenges or value creation across the Union’. Paragraphs 15
88
89
90
91
92
19
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
to 19 of that communication set out the criteria to be met in order for those
requirements to be satisfied. In that regard, paragraph 15 of the IPCEI
Communication states that, in order to be regarded as representing an important
contribution to the European Union’s objectives, the project must, inter alia, be of
major importance for the Trans-European transport and energy networks.
Paragraph 16 of the IPCEI Communication states, first, that the project must
normally involve more than one Member State and its benefits must not be
confined to the financing Member States, but extend to a wide part of the
European Union and, second, that the benefits of the project must be clearly
defined in a concrete and identifiable manner. Furthermore, according to
paragraph 17 of that communication, those benefits must not be limited to the
undertakings or to the sector concerned but must be of wider relevance and
application to the European economy or society through positive spillover effects
(such as having systemic effects on multiple levels of the value chain, or up- or
downstream markets, or having alternative uses in other sectors or modal shifts)
which are clearly defined in a concrete and identifiable manner. Moreover, in
accordance with paragraph 18 of the IPCEI Communication, the project must
involve co-financing by the beneficiary and, according to paragraph 19 thereof, it
must respect the principle of the phasing out of environmentally harmful
subsidies.
93
Next, for the purposes of the classification as a project of common European
interest, paragraph 3.2.2 of the IPCEI Communication sets out general positive
indicators justifying a more favourable approach by the Commission. Those
indicators include, in paragraph 20(f) of that communication, co-financing of the
project by an EU fund.
Lastly, paragraph 3.2.3 of the IPCEI Communication sets out specific criteria,
including that laid down in paragraph 23 of that communication, according to
which environmental, energy or transport projects must either be of great
importance for the environmental, energy or transport strategy of the European
Union or contribute significantly to the internal market, including, but not limited
to, those specific sectors.
In the present case, first, in recital 272 of the contested decision, the Commission
stated that the Fixed Link project was of major importance for the Trans-European
Transport (TEN-T) network and that it would contribute to the development of the
TEN-T. Since the applicants have not disputed that assessment and there is
nothing to call it into question, the Commission was therefore entitled to consider
that that criterion referred to in paragraph 15 of the IPCEI Communication was
satisfied. In addition, since it is a priority European transport network project, the
particular criterion referred to in paragraph 23 of that communication, according
to which transport projects must be of great importance for the European Union’s
transport strategy, is also satisfied.
Second, it must be held that the criteria laid down in paragraph 16 of the IPCEI
Communication are also satisfied. On the one hand, in recital 272 of the contested
94
95
96
20
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
decision, the Commission stated, without it being disputed, that the Fixed Link
would contribute to an improvement of the connection between the Nordic
countries and central Europe as well as to greater flexibility and time savings for
road and railway traffic, with the result that the Commission was entitled to take
the view that the benefits generated by the project were defined in a concrete and
identifiable manner. On the other hand, in recital 273 of the contested decision,
the Commission rightly stated that the project involved the Kingdom of Denmark
and the Federal Republic of Germany and that its benefits went beyond those two
countries since the benefits extended to all the countries crossed by the
Scandinavian-Mediterranean corridor from Finland to the island of Malta.
97
Third, since the Commission found, without it being called into question, in
recital 273 of the contested decision, that the Fixed Link project was aimed at
improving the conditions for transport not only of passengers but also of goods
between the Nordic countries and central Europe and that the project would close
the missing link on the Scandinavian-Mediterranean corridor, which, according to
footnote 135, is ‘a crucial north-south axis for the European economy’, it must be
held that the criterion laid down in paragraph 17 of the IPCEI Communication is
also satisfied on that basis. In view of the fact that the benefits of the Fixed Link
project contribute to improving the conditions for transport of both passengers and
goods on an important European economy axis, the Commission was entitled to
take the view that the benefits of the Fixed Link are not limited to the undertaking
concerned, namely Femern, or to the sector concerned, namely transport services,
for the crossing of the Fehmarn Belt. Furthermore, the Commission was also
entitled to consider that the benefits of the project were of wider relevance and
application in the European economy or society in the form of positive impacts
clearly defined in a concrete and identifiable manner, namely, as is already
apparent, in essence, from recitals 272 and 273 of the contested decision, an
improvement in the functioning of the internal market and a strengthening of
economic and social cohesion. It must be stated that the applicants, NABU,
Aktionsbündnis, ECSA and Rederi Nordö-Link do not dispute those benefits
which are generated by the Fixed Link and identified by the Commission in
recital 281 of the contested decision.
Fourth, as follows from paragraphs 82 to 84 above, the Commission was entitled
to consider that the Fixed Link was co-financed by Femern, with the result that the
criterion laid down in paragraph 18 of the IPCEI Communication is satisfied.
Fifth, as regards the criterion laid down in paragraph 19 of the IPCEI
Communication, the application does not contain, as has already been pointed out,
any complaint challenging the finding in recital 279 of the contested decision that
the Fixed Link does not relate to environmentally harmful subsidies and does not
conflict with the principle of the phasing out of such subsidies, with the result that
that criterion can be considered to be satisfied.
98
99
100 Sixth, it should be noted that, in recital 280 of the contested decision, the
Commission stated that the Fixed Link project had, without this being challenged,
21
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
received EU funding for planning activities and a commitment for further support
under the Connecting Europe Facility (CEF). In accordance with paragraph 20(f)
of the IPCEI Communication, obtaining such EU funding is a positive indicator
justifying a more favourable approach.
101 It follows from the foregoing considerations that the general criteria laid down in
paragraphs 14 to 19 of the IPCEI Communication were met without it being
necessary to rely on the results of the Incentive studies disputed by the applicants,
NABU, Aktionsbündnis, ECSA and Rederi Nordö-Link. Furthermore, since the
Commission also relied on one of the general positive indicators referred to in
paragraph 20 of that communication, it was entitled to conclude, in recital 281 of
the contested decision, that the Fixed Link project represented an important and
concrete contribution to the achievement of the European Union’s transport policy
objectives and broader EU objectives, in particular the strengthening of economic
and social cohesion, with the result that that project is of common European
interest.
102 As regards the argument of the applicants, NABU, Aktionsbündnis, ECSA and
Rederi Nordö-Link that the Commission could not reach the conclusion that the
Fixed Link project was of common European interest within the meaning of the
IPCEI Communication without relying on the Incentive studies, it must be noted
that, first, it is apparent from recital 274 of the contested decision that the benefits
of the Fixed Link project, which were already clearly defined in recitals 272 and
273 of that decision, ‘have been further specified’ in the Incentive studies.
Second, as regards the quantification of the benefits carried out in recitals 275 to
277 of the contested decision, as the Commission rightly submits, it must be noted
that neither Article 107(3)(b) TFEU nor the IPCEI Communication requires that
the benefits of a project be quantified in the context of a socioeconomic analysis
of the costs and benefits for the purposes of classifying a project as a project of
common European interest. Therefore, as the Commission stated in its rejoinder, it
must be held that the results of the Incentive studies were mentioned in
recitals 275 to 277 of the contested decision as additional information that was
useful, but not essential, for the purposes of classifying the Fixed Link project as a
project of common European interest.
103 It follows that the first and second complaints, by which the applicants, NABU,
Aktionsbündnis, ECSA and Rederi Nordö-Link merely challenge the
quantification of the benefits of the Fixed Link, are directed against grounds
which are included in the contested decision for the sake of completeness.
104 Consequently, those complaints must be rejected as ineffective.
105 The first part of the second plea must therefore be rejected in its entirety.
22
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
2.
The second part, alleging that the Commission was wrong to conclude that
the aid was necessary
106 By the second part, the applicants raise three complaints, first, alleging that the aid
had no incentive effect, second, alleging that the Commission was wrong to find
that the counterfactual scenario consisted in the absence of an alternative project
and, third, challenging the periods used for the purposes of calculating the internal
rate of return (‘the IRR’).
(a)
The first complaint, alleging that the aid had no incentive effect
107 The applicants, supported by DFA, ECSA, Trelleborg Hamn and Rederi Nordö-
Link, submit that the Commission was wrong to find that the aid had an incentive
effect.
108 The Commission, supported by the Kingdom of Denmark, disputes those
arguments.
109 In that regard, it must be noted that Article 107(3)(b) TFEU provides, inter alia,
that aid to promote the execution of an important project of common European
interest may be considered to be compatible with the internal market.
110 Within the discretion conferred on it by Article 107(3)(b) TFEU, the Commission
is entitled to refuse the grant of aid where that aid does not induce the recipient
undertakings to adopt conduct likely to assist attainment of one of the objectives
referred to in that provision (see, to that effect, judgment of 19 July 2016,
Kotnik
and Others,
C-526/14, EU:C:2016:570, paragraph 49 and the case-law cited).
111 Such aid must thus be necessary for the attainment of the objectives specified in
that provision, with the result that, without it, market forces alone would not
succeed in getting the recipient undertakings to adopt conduct likely to assist
attainment of those objectives. Aid which improves the financial situation of the
recipient undertaking without being necessary for the attainment of the objectives
specified in Article 107(3) TFEU cannot be considered compatible with the
internal market (see, by analogy, judgment of 13 June 2013,
HGA and Others
v
Commission,
C-630/11 P to C-633/11 P, EU:C:2013:387, paragraph 104 and the
case-law cited).
112 Thus, in the context of Article 107(3)(b) TFEU, in order to be compatible with the
internal market, the planned aid must have an incentive effect and thus be
necessary for the execution of an important project of common European interest.
To that end, it must be demonstrated that, in the absence of the planned aid, the
investment intended to implement such a project would not take place. If, on the
other hand, it appears that that investment would take place even without the
planned aid, the conclusion must be that the aid serves merely to improve the
financial situation of the recipient undertakings, without, however, meeting the
requirement in Article 107(3)(b) TFEU that it is necessary for the execution of an
23
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
important project of common European interest (see, to that effect and by analogy,
judgments of 13 June 2013,
HGA and Others
v
Commission,
C-630/11 P to
C-633/11 P, EU:C:2013:387, paragraph 105; of 13 December 2017,
Greece
v
Commission,
T-314/15, not published, EU:T:2017:903, paragraph 182; and of
12 September 2019,
Achemos Grupė and Achema
v
Commission,
T-417/16, not
published, EU:T:2019:597, paragraph 84).
113 Lastly, it must be noted that, in accordance with the case-law, a finding that an aid
measure is not necessary can arise in particular from the fact that the aid project
has already been started, or even completed, by the undertaking concerned prior to
the application for aid being submitted to the competent authorities. In such a
case, the aid concerned cannot operate as an incentive (judgments of 15 April
2008,
Nuova Agricast,
C-390/06, EU:C:2008:224, paragraph 69, and of
12 September 2019,
Achemos Grupė and Achema
v
Commission,
T-417/16, not
published, EU:T:2019:597, paragraph 85).
114 It is in the light of those considerations that the arguments raised by the
applicants, DFA, ECSA, Trelleborg Hamn and Rederi Nordö-Link must be
examined.
115 As a preliminary point, it must be noted that, in the contested decision and in the
parties’ pleadings, the concepts of ‘formal incentive effect’ and ‘substantive
incentive effect’ are used. For the sake of clarity and terminological precision, for
the purposes of the present judgment, first, the concept of ‘formal incentive effect’
must be understood as being the criterion that ‘the aid application must precede
the start of the work’ (see, to that effect, judgments of 13 June 2013,
HGA and
Others
v
Commission,
C-630/11 P to C-633/11 P, EU:C:2013:387, paragraph 106,
and of 5 March 2019,
Eesti Pagar,
C-349/17, EU:C:2019:172, paragraph 64).
Second, the requirement of a ‘substantive incentive effect’ must be understood as
being the condition of ‘the incentive effect of the aid’ referred to in the case-law
cited in paragraph 112 above, namely the incentive for the beneficiary to adopt
conduct likely to contribute to the attainment of the objectives of Article 107(3)(b)
TFEU.
116 In the IPCEI Communication, the requirement that aid must satisfy the condition
of having an incentive effect is set out in paragraph 28, and footnote 24 to that
paragraph repeats the criterion that the application must be made beforehand,
namely ‘the aid application must precede the [start] of the works’.
117 It is necessary to ascertain whether, as the applicants, Trelleborg Hamn and ECSA
claim, the Commission committed a manifest error of assessment in finding that,
in the circumstances of the present case, the aid application was inherent in the
establishment of Femern.
118 In the present case, in recitals 299 and 302 of the contested decision, the
Commission considered that satisfaction of the criterion that the aid application
must be submitted beforehand, as defined in the IPCEI Communication, was not a
24
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
necessary prerequisite on the ground that the incentive effect condition was
satisfied by the demonstration that the project at issue could not be completed
without aid. According to the Commission, a distinction must be drawn between
an undertaking such as Femern which receives aid in order to carry out the link
project defined by the public authorities and the other undertakings that may
decide on the projects in which they wish to invest. Thus, in view of the particular
features of the present case, the Commission took the view that, even in the
absence of an aid application formally submitted by Femern to the Danish
authorities, the criterion that the aid application must be submitted beforehand was
satisfied on the ground that such an application could be regarded as inherent in
the establishment of that entity.
119 It should be noted that Femern is a specific-purpose company that was created by
the public authorities to carry out a particular project to the exclusion of any other
activity. As the Kingdom of Denmark has submitted, such an entity does not
receive operating income until the end of construction works. Therefore, until the
Fixed Link is brought into operation, Femern is dependent on the financing
granted by the public authorities, in particular to carry out the construction of the
infrastructure. Such a situation is not comparable with those of private or public
undertakings that may determine the projects in which they wish to invest and
finance them, at least in part, using income generated by their other activities.
120 In addition, in the present case, it must be noted that, on 22 December 2014, the
Kingdom of Denmark notified all the financing which that entity had received
since its creation in 2005 in order for that financing’s compatibility with the
internal market to be assessed by the Commission on the basis of
Article 107(3)(b) TFEU and the criteria set out in the IPCEI Communication. In
that regard, it must be noted that, on the basis of Paragraph 6 of the lov nr 588 om
Sund og Bælt Holding A/S (Law No 588 on Sund & Baelt Holding A/S) of
24 June 2005, Femern, formerly Femern Bælt A/S, was established in order to
carry out the tasks relating to the planning of the Fixed Link, to the exclusion of
all other activities. For its establishment, that entity received a capital injection in
2005. Next, after the signature of the Fehmarn Belt Treaty, on the basis of the
2009 Planning Law, Femern received an additional capital injection as well as
State loans and State guarantees. By its decision of 13 July 2009 in Case
N 157/2009, the Commission found, primarily, that the financing granted to
Femern did not constitute State aid within the meaning of Article 107(1) TFEU
and, as a precautionary measure, if that entity were to be required to operate the
Fixed Link economically, that that funding would constitute aid compatible with
the internal market on the basis of Article 107(3)(b) TFEU. It must be noted that
that decision has not been challenged.
121 Thus, since the Commission was entitled to examine jointly the compatibility of
all the financing necessary for the completion of the Fixed Link project since the
establishment of Femern (see paragraphs 53 to 61 above) and in so far as that
undertaking will not receive operating revenue until the Fixed Link becomes
operational, it cannot be required that the criterion that the aid application must be
25
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
submitted beforehand be verified for each of the three individual aids granted to
Femern to carry out the Fixed Link project. Furthermore, in the present case, the
Commission was entitled to consider that the aid application was inherent in the
establishment of Femern.
122 In order to challenge that conclusion, in the first place, the applicants, Trelleborg
Hamn, DFA, ECSA and Rederi Nordö-Link submit, in essence, that, at the time of
its creation, Femern was responsible only for the planning of the Fixed Link and
that it was only subsequently that Femern became responsible for the construction
and operation of that infrastructure.
123 In that regard, as the Commission rightly submits, since Femern was set up in
order to carry out the Fixed Link project, the fact that its activities have evolved
since its establishment is irrelevant for the purposes of calling into question the
fact that the aid application may be regarded as being inherent in its establishment.
124 The entire project was entrusted by the public authorities to the same specific-
purpose company that is not authorised to carry out activities other than those
relating to that project.
125 In respect of the works regarded by the applicants, Trelleborg Hamn and ECSA as
construction works carried out in 2013 and 2014, as the Commission observed in
recital 300 of the contested decision, those works were covered by increases in the
planning budget granted by the Danish Parliament’s Finance Committee on 3 June
2010, 23 June 2011 and in March 2013. It is apparent from the elements in the
file, in particular from the application for budget appropriations No 97 of
13 March 2013 annexed to the statement in intervention of the Kingdom of
Denmark, that the works carried out from September 2013 had been the subject of
a prior financial assessment by Femern, on the basis of which the Danish Minister
for Transport had requested the approval of the Danish Parliament’s Finance
Committee for an increase in the planning budget. It must also be noted that the
financing model for the Fixed Link notified by the Danish authorities on
22 December 2014, which included, as is apparent from recital 36 of the contested
decision, an estimate of the total cost of the planning and construction of the Fixed
Link, had been preceded by a financial analysis carried out by Femern in
November 2014. Similarly, it must be noted that the funding gap calculated in the
contested decision in the context of the examination of the proportionality of the
aid is based on an updated financial analysis also carried out by Femern.
126 Thus, since Femern, as a specific-purpose company, is dependent on public
financing in order to carry out the tasks entrusted to it, even if, as the applicants
submit, the Commission should have examined separately whether the criterion
that the aid application must be submitted beforehand had been satisfied because
of the evolution of Femern’s activities, it would have been possible for the
Commission to find that the works undertaken, whether classified as ‘construction
works’ or as ‘preparatory work’, had been carried out following an application in
the form of an assessment of Femern’s financing needs.
26
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
127 Contrary to what the applicants submit, it is clear from the wording of footnote 24
to paragraph 28 of the IPCEI Communication that it is sufficient for the aid
application to precede the start of the works. Therefore, the beneficiary of the aid
is not required to wait for the approval of that application or for the grant of the
aid before commencing the work. That requirement of the IPCEI Communication
is not comparable to that of other guidelines, interpreted in the judgments of
5 March 2019,
Eesti Pagar
(C-349/17, EU:C:2019:172), and of 13 September
2013,
Fri-El Acerra
v
Commission
(T-551/10, not published, EU:T:2013:430),
relied on by the applicants, which expressly required written confirmation from
the national competent authorities.
128 Furthermore, as the Commission is fully entitled to submit, the question of
whether the criterion that the aid application must be submitted beforehand is
satisfied bears no relation to the question of whether the aid was paid unlawfully
in breach of Article 108(3) TFEU or to the question of whether the financing was
granted to Femern in breach of the Planning Decision.
129 In the second place, the applicants, DFA and Trelleborg Hamn submit that the
possibility of recognising that the aid application may be regarded as inherent in
the establishment of Femern constitutes discrimination in favour of public
undertakings that is prohibited by Article 345 TFEU, which amounts, in essence,
to relying on a breach of the principle of equal treatment.
130 In that regard, it should be noted that, according to the case-law, the general
principle of equal treatment, as a general principle of EU law, requires that
comparable situations must not be treated differently and different situations must
not be treated in the same way unless such treatment is objectively justified.
Moreover, the burden of proving the comparability of situations lies with the
person pleading it (see, to that effect, judgments of 8 April 2014,
ABN Amro
Group
v
Commission,
T-319/11, EU:T:2014:186, paragraphs 110 and 114, and of
21 December 2021,
Gmina Kosakowo
v
Commission,
T-209/15, not published,
EU:T:2021:926, paragraph 152).
131 According to the applicants, DFA and Trelleborg Hamn, since a private
undertaking cannot be a specific-purpose company owned by the State, the finding
that the aid application is inherent in the establishment of Femern on the ground
that it is a specific-purpose company owned by the State constitutes
discrimination in favour of public undertakings.
132 In that regard, as the Commission and the Kingdom of Denmark rightly submit, it
must be held that specific-purpose entities created by public authorities in order to
carry out a project in the public interest are not in a situation that is comparable
with the specific-purpose entities created by private undertakings. Whereas
specific-purpose entities owned by private persons may be established without
public financing capable of being classified as State aid, in certain cases the
establishment of a specific-purpose entity by the public authorities involves the
payment of public financing, which must be classified as aid where it is not
27
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
granted under market conditions. It follows that, as the Commission and the
Kingdom of Denmark have argued, it would be artificial to require the public
authorities to establish a specific-purpose entity and for the latter formally to
submit an application for aid in order for it to be established.
133 Consequently, since the situations are not comparable, there cannot be a
difference in treatment constituting a breach of the principle of equal treatment.
134 As regards the arguments of the applicants, DFA, Trelleborg Hamn and Rederi
Nordö-Link alleging that there was a disregard of the Commission’s decision-
making practice, it should be noted that, according to the case-law, it is in the light
of Article 107(3)(b) TFEU – and not of the Commission’s previous practice – that
it must be assessed whether or not aid satisfies the conditions laid down by that
provision for its application (see, by analogy, judgments of 21 July 2011,
Freistaat Sachsen and Land Sachsen-Anhalt
v
Commission,
C-459/10 P, not
published, EU:C:2011:515, paragraph 38, and of 22 September 2020,
Austria
v
Commission,
C-594/18 P, EU:C:2020:742, paragraph 25). Moreover, an
examination of the decisions relied on does not reveal any established practice on
the part of the Commission as regards the criterion of the prior submission of the
aid application being applied to specific-purpose entities owned by private
persons. The arguments based on those decisions must therefore be rejected.
135 In the third place, since, in the particular circumstances of the present case,
satisfaction of the criterion that the aid application must be submitted beforehand
could validly be established upon the finding that the aid application was inherent
in the establishment of Femern, the applicants’ argument, to the effect that
recognition of the possibility that an aid application is inherent in the
establishment of an entity such as Femern would mean that the incentive effect
condition laid down in paragraph 28 of the IPCEI Communication would never be
applied to large infrastructure projects carried out by ad hoc entities entrusted with
their construction, must be rejected as ineffective.
136 Furthermore, in so far as, by the argument referring to the receipt of EU financing
under the TEN-T programme, the applicants seek to argue that obtaining such
financing proves that aid was not necessary in order to complete the work carried
out in 2013 and 2014, it must be held that such an argument is irrelevant in the
context of the application of the criterion that the aid application must be
submitted beforehand. In any event, it must be stated that such an argument,
which forms part of the assessment of the incentive effect condition, tends more to
support the finding that such a project cannot be carried out without aid.
137 It therefore follows from the foregoing that, in the absence of discrimination, the
Commission did not err in law and did not make a manifest error of assessment in
concluding that the aid had an incentive effect.
138 Accordingly, the first complaint, alleging that the aid had no incentive effect, must
be rejected.
28
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
(b)
The second complaint, alleging that the Commission was wrong to find
that the counterfactual scenario consisted in the absence of an alternative
project
139 The applicants, FSS, Aktionsbündnis, NABU and VDR submit that the
Commission erred in law and made a manifest error of assessment in finding that
the counterfactual scenario consisted in the absence of an alternative project.
140 The Commission, supported by the Kingdom of Denmark, rejects that line of
argument.
141 In that regard, it must be noted that, for the purposes of the assessment of the
necessity of the aid, paragraph 29 of the IPCEI Communication provides that the
Member State must provide the Commission with adequate information
concerning the aided project as well as a comprehensive description of the
counterfactual scenario which corresponds to the situation where no aid is
awarded by any Member State, and the counterfactual scenario may consist in the
absence of an alternative project or in a clearly defined and sufficiently
predictable alternative project considered by the beneficiary in its internal
decision-making, and that it may relate to an alternative project that is wholly or
partly carried out outside the European Union.
142 In the contested decision, in reaching the conclusion that the counterfactual
scenario consists in the absence of an alternative project, the Commission relied
on the information provided by the Danish authorities to demonstrate that there
was no credible or realistic counterfactual description of an alternative project.
Thus, in recital 307 of the contested decision, the Commission relied on a report,
drawn up in 2001, on the commercial interest of the Fixed Link project (‘the 2001
commercial interest report’) in order to find that, in view of the substantial risks
associated with a Fixed Link project, the requirements set out by the private sector
were such that capital costs would have been so high that the project would not
have been feasible without substantial public support. On the basis of information
provided by the Danish authorities at the time of the notification of the financing
of the Fixed Link, the Commission considered that that conclusion had not
changed in the meantime. Thus, in recital 308 of the contested decision, the
Commission found that no rational private investor would engage in such a project
under normal market conditions and that the Fixed Link could be completed only
with substantial public support. In addition, the Commission stated that the fact
that the final technical solution had changed since the 2001 commercial interest
report did not alter that conclusion and that nothing suggested that a
counterfactual scenario without aid had become viable in the meantime. In
addition, the Commission considers that the provision of EU financial assistance
under the CEF is a strong indication of the necessity of public funding for the
realisation of the project.
143 In the first place, it is necessary to ascertain whether, as the applicants, FSS,
Aktionsbündnis, NABU and VDR submit, the Commission failed to take account
29
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
of alternative projects capable of constituting a counterfactual scenario within the
meaning of paragraph 29 of the IPCEI Communication.
144 First, as regards a project for an improved ferry system, the applicants rely on the
cost-benefit report drawn up in 2000 by the consultancy firm Planco (‘the Planco
report’), which contained several alternatives to the current version of the Fixed
Link project, including a project for an improved ferry system.
145 It should be noted that the Planco report does not contain any clear indication as to
whether or not the improvement of ferry services requires the grant of aid. In that
regard, the applicants acknowledged at the hearing that that report was not
intended to determine whether the projects to which it refers could be completed
without aid. In addition, it must be noted that, in recital 306 of the contested
decision, the Commission considered that it was apparent from the Planco report
that the absolute magnitude of net benefits gained by the Fixed Link solution
could not be achieved by an improved ferry system, in particular as regards a
reduction in travelling time and savings in transport costs. Consequently, the
Commission concluded that an improved ferry system was not an alternative
solution with the same scope and achieving comparable expected benefits as the
Fixed Link project.
146 In that regard, for the purposes of interpreting the requirement for a counterfactual
scenario, account must be taken of paragraph 28 of the IPCEI Communication,
which states that, without the aid, the project’s realisation would be impossible, or
it would be realised in a smaller size or scope or in a different manner that would
significantly restrict its expected benefits. Thus, where a project is not of a
comparable size or scope or would significantly restrict benefits expected from the
aided project, the Commission does not disregard the IPCEI Communication by
finding that such a project does not constitute an alternative project capable of
constituting a counterfactual scenario within the meaning of paragraph 29 of that
communication.
147 In the present case, it should be noted that, as is apparent in particular from
recitals 33 and 272 of the contested decision, the Fixed Link project must
contribute to filling a missing link on the Scandinavian-Mediterranean corridor, to
improving the connection between the Nordic countries and central Europe and to
increasing flexibility and time savings for road and railway traffic.
148 It is true that, as NABU and VDR submit, in the original version of the Incentive
studies, the main benefit of the Fixed Link came from its operating revenue.
However, without there being any need to rule on the possibility of comparing the
results of the Planco report with those of the Incentive studies, it is sufficient to
note that, as regards road traffic, it is apparent from the initial version of the
Incentive studies that the Fixed Link will reduce the time taken to cross the
Fehmarn Belt to 10 minutes by passenger car, as opposed to 45 minutes by ferry,
and that it will increase flexibility in that it will not be necessary to wait for a ferry
departure. In addition, that study also highlights the benefits of the Fixed Link for
30
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
the improvement of railway transport, such as the reduction in train journey time
between Germany and Denmark.
149 Thus, since a project for an improved ferry system would not be capable of
attaining the objectives pursued by the Fixed Link project, the fact that the rate of
return from a project for an improved ferry system is higher than the rate of return
from a fixed link is irrelevant. In the examination of the existence of an alternative
project, neither the Danish authorities nor the Commission can be criticised for
not having taken into account a project that is not suitable for attaining the public
interest objectives pursued by the public authorities.
150 It follows that the Commission has not made a manifest error of assessment in
finding that an improved ferry service would not offer the same benefits as a fixed
link in terms of reduced journey times and savings in transport costs. Accordingly,
the Commission cannot be criticised for having failed to take into account the
project for an improved ferry system.
151 Second, as regards the alternative fixed links referred to by the applicants, in
particular those envisaged by the Planco report, namely a suspension bridge, a
cable-stayed bridge and several configurations of bored tunnels and immersed
tunnels, the applicants acknowledged at the hearing, as stated in paragraph 145
above, that that report was not aimed at determining whether the projects to which
it refers could be carried out without aid.
152 As regards the solution consisting of a cable-stayed bridge and an immersed
tunnel comparable to that at issue in the present case, set out in the report on the
economic assessment of the Fehmarn Belt fixed link drawn up in March 2004 by
the consultancy firm COWI (‘the COWI report’), it must be noted that NABU,
Aktionsbündnis and VDR do not refer to any specific passage in that report
annexed to the application. When questioned at the hearing, the applicants were
unable to indicate which extract from that report could demonstrate that the
projects to which it refers could be completed without aid. In any event, it must be
stated that it is not apparent from the summary of that report, which was translated
into the language of the case, that the solution of a cable-stayed bridge or an
immersed tunnel could be completed without aid. On the contrary, that report
starts from the premiss that such a project would receive EU financing amounting
to approximately 10% of the investment costs, with the result that that financing
would have a positive impact on the costs borne by the Kingdom of Denmark and
the Federal Republic of Germany.
153 The same finding may be made as regards the report on the environmental impact
of the Fixed Link, carried out by Femern and relied on by FSS, Aktionsbündnis,
NABU and VDR. It is true that, in that report, several alternatives were envisaged,
namely a cable-stayed bridge, a suspension bridge and a bored tunnel. However,
the interveners have not demonstrated that it is apparent from the extracts from
that report, translated into the language of the case, that those alternative projects
could be completed without aid.
31
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
154 Consequently, the Commission cannot be criticised for not having taken into
account alternative fixed link projects.
155 Third, as regards the project consisting of an upgrade of the Jutland (Denmark)
route, relied on by the applicants, it must be noted that the reference to page 5 of
the summary of the COWI report is incorrect, since the summary of that report
translated into the language of the case does not refer to such a project. As regards
the project relied on by NABU, which consists of an upgrade of ferry services
across the Fehmarn Belt and an upgrade of the existing railways through Jutland,
it must also be stated that such a project does not appear in the summary of the
COWI report, translated into the language of the case, to which no specific
reference is made in the statement in intervention. In addition, as regards the
project relied on by NABU, which is the improvement of a Jutland rail link
passing through Kolding (Denmark), it must be noted that the statement in
intervention does not contain sufficient details to enable that project to be
identified. Therefore, the mere reference to those projects relied on by the
applicants and NABU does not demonstrate that the Commission was wrong not
to take them into account.
156 It follows from the foregoing considerations that the applicants, FSS,
Aktionsbündnis, NABU and VDR have not demonstrated that the findings made
in recitals 306 to 308 of the contested decision and the conclusion that the
counterfactual scenario consists in the absence of an alternative project were
vitiated by a manifest error of assessment.
157 In the second place, the Court cannot accept FSS’ argument that, in essence, it is
apparent from paragraph 150 of the judgment of 12 July 2018,
Austria
v
Commission
(T-356/15, EU:T:2018:439), and from paragraph 29 of the IPCEI
Communication that a Member State cannot channel aid towards a project of its
choosing where there are clearly defined and sufficiently predictable alternative
projects which meet the same objectives and require a lower amount of aid.
158 First, it must be stated that that line of argument has no basis in the judgment of
12 July 2018,
Austria
v
Commission
(T-356/15, EU:T:2018:439).
159 Second, as the Commission stated, where there is an important project of common
European interest, provided that the conditions laid down in Article 107(3)(b)
TFEU and those laid down in the IPCEI Communication are satisfied, a Member
State is free to grant aid to a project of its choosing.
160 In the third place, contrary to what the applicants claim, in order to conclude that,
in the present case, the counterfactual scenario consists in the absence of an
alternative project, the Commission did not rely on the finding in the third
sentence of recital 304 of the contested decision that, as a specific-purpose
company established to complete the Fixed Link, Femern has no power to decide
to carry out an alternative project of a different scale. As is apparent from
recitals 306 to 308 of the contested decision, in order to reach that conclusion, the
32
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
Commission relied on the information submitted by the Danish authorities
according to which there is no project comparable to the Fixed Link that could be
carried out without aid.
161 Since the applicants, FSS, Aktionsbündnis, NABU and VDR have not succeeded
in demonstrating that there is an alternative project which is of a comparable size
or scope or which provides benefits equivalent to those expected from the Fixed
Link project and which could be carried out without aid, there can be no
difference in treatment in favour of a public undertaking. Paragraph 29 of the
IPCEI Communication expressly provides that the counterfactual scenario may
consist in the absence of an alternative project in respect of projects such as that at
issue in the present case, for which, due to the high investment costs and risks, no
private investor would commit to under normal market conditions. Therefore, if
the public authorities were to entrust a private undertaking with carrying out such
a project, there would also be no disregarding of the IPCEI Communication if it
were validly established that the counterfactual scenario consisted in the absence
of an alternative project. It follows that Aktionsbündnis, NABU and VDR cannot
maintain that the Commission breached infringed the principle of equal treatment.
162 Lastly, as regards the argument put forward by NABU and Aktionsbündnis that, in
essence, the Fixed Link project is more harmful to the environment than improved
ferry services, it must be held that such considerations are irrelevant for the
purpose of determining whether there is an alternative project capable of being
carried out without aid. Moreover, there is no evidence to support the argument as
to the alleged harmful effects of the Fixed Link on the environment or the
argument regarding the supposed beneficial effects of ferries on carbon dioxide
(CO
2
) emissions.
163 It follows from the foregoing considerations that the Commission did not err in
law or make a manifest error of assessment in finding that the counterfactual
scenario consisted in the absence of an alternative project.
164 Accordingly, the second complaint, alleging that the Commission was wrong to
find that the counterfactual scenario consisted in the absence of an alternative
project, must be rejected as unfounded.
(c)
The third complaint, challenging the periods used for the purposes of
calculating the IRR (necessity of the aid) and of calculating the funding
gap (proportionality of the aid)
165 The applicants, FSS, ECSA, Trelleborg Hamn and VDR submit that the lifetime
of the investment, provided for in paragraph 31 of the IPCEI Communication, for
the purposes of calculating the funding gap should correspond to the lifetime of
the project, provided for in paragraph 30 of that communication, in order to
calculate the IRR. Therefore, the applicants and those interveners rely on the same
arguments in support of the complaint, put forward in the part concerning the
necessity of the aid, alleging a manifest error of assessment of the period used for
33
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
the purposes of calculating the IRR and in support of the complaint, put forward
in the third part concerning the proportionality of the aid, alleging a manifest error
of assessment of the period used for the purposes of calculating the funding gap.
166 The applicants, FSS, ECSA, Trelleborg Hamn and VDR submit that the
Commission made manifest errors of assessment in relying on a period of 40 years
for the calculation of the IRR and the funding gap. According to them, by using
120 years for the lifetime of the project, first, the IRR was higher because the
revenue generated by the Fixed Link was higher over time and, second, the
funding gap was lower.
167 The Commission, supported by the Kingdom of Denmark, rejects that line of
argument.
168 In that regard, it should be noted that, first, in the absence of an alternative project,
according to paragraph 30 of the IPCEI Communication, the Commission must
verify that the aid amount does not exceed the minimum necessary for the aided
project to be sufficiently profitable, for example by making it possible to achieve
an IRR corresponding to the sector- or firm-specific benchmark or hurdle rate, and
all relevant expected costs and benefits must be considered over the lifetime of the
project. It follows that the aid is necessary if the project is not profitable during its
lifetime (see, to that effect, judgment of 13 December 2018,
Scandlines Danmark
and Scandlines Deutschland
v
Commission,
T-630/15, not published,
EU:T:2018:942, paragraph 210).
169 Second, in accordance with paragraph 31 of the IPCEI Communication, the
maximum aid level is determined with regard to the identified funding gap in
relation to the eligible costs and, if justified by the funding gap analysis, the aid
intensity could reach up to 100% of the eligible costs. That same paragraph
defines the funding gap as the difference between the positive and negative cash
flows over the lifetime of the investment, discounted to their current value on the
basis of an appropriate discount factor reflecting the rate of return necessary for
the beneficiary to carry out the project notably in view of the risks involved.
170 In the present case, it is apparent from recital 327 of the contested decision that,
for the purposes of determining the funding gap, the Danish authorities used an
expected economic lifetime of 40 years, on the ground that it is the timespan that
an investor would normally consider when investing in a large-scale infrastructure
such as the Fixed Link. Although the Commission stated that Femern’s website
indicated a project lifetime of 120 years, the Commission nevertheless noted that
when cash flows are distant, the impact of the discounting is significant. In
addition, it considered that, due to the high degree of uncertainty surrounding any
financial forecast over such a very long period of time, it is unlikely that any
reasonable investor would accept to make an investment whose profitability
prospects can be realised only over such a very long period of time. Therefore, the
Commission considered that an operational period of 40 years was a reasonable
assumption for the calculation of the funding gap of the Fixed Link.
34
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
171 As regards the IRR, in recitals 309 and 310 of the contested decision, since
Femern does not have an investment project of a similar kind or overall cost of
capital that could be used to calculate whether the aid amount exceeds the level
necessary for the project to be sufficiently profitable, the Commission considered
that it was appropriate to compare the IRR from the Fixed Link project, without
aid, with the cost of capital requirements seen in the industry concerned, namely a
5.59% weighted average cost of capital (‘WACC’). Thus, it is apparent from
recital 312 of the contested decision that, by using 40 years for the economic
lifetime of the investment, the Commission found that the IRR of the project
without aid was 3.9% and that it would remain below the WACC even with a
longer lifetime until 2100.
172 It should be noted that, by their line of argument, the applicants, FSS, ECSA,
Trelleborg Hamn and VDR complain that the Commission calculated the IRR and
the funding gap by using 40 years as the economic lifetime of the investment
instead of a project lifetime of 120 years.
173 In that regard, in the first place, it should be noted that, in paragraph 213 of the
judgment of 13 December 2018,
Scandlines Danmark and Scandlines
Deutschland
v
Commission
(T-630/15, not published, EU:T:2018:942), the Court
held that, when referring to the ‘repayment period for the aid’, the Commission
had failed to apply correctly paragraph 30 of the IPCEI Communication, which
states that the IRR is to be calculated taking into account all expected costs and
benefits over the ‘lifetime of the project’. Furthermore, the Court considered that,
to base the calculation of the IRR on a very uncertain repayment period was also
arbitrary, as that period may vary depending on subjective factors, including the
type of aid and the arrangements for repayment negotiated between the
beneficiary and the financial institution granting the loan.
174 Contrary to what is claimed by the applicants, ECSA, Trelleborg Hamn and VDR,
it cannot be inferred from those considerations that the Court intended to require
the Commission to take into account a period of 120 years for the calculation of
the IRR, particularly since, in the judgment of 13 December 2018,
Scandlines
Danmark and Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), the only reference to that period appears in the conditional tense
in the parties’ arguments. In addition, it must be noted that, in paragraph 217 of
that judgment, the Court held that it could not be ruled out, in principle, that aid
was necessary for the realisation of such a large project, but that an insufficient
and imprecise examination of the necessity of the aid had indicated that there were
serious difficulties, which should have prompted the Commission to initiate the
formal investigation procedure, and which meant that it was not possible for the
Court to examine whether the Commission had made a manifest error of
assessment.
175 In the second place, it is necessary to ascertain whether, as the applicants, FSS,
ECSA, Trelleborg Hamn and VDR claim, the Commission disregarded
paragraphs 30 and 31 of the IPCEI Communication by taking into account the
35
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
conduct of investors on the market for the determination of the relevant period for
the calculation of the IRR and the funding gap.
176 First, for the relevant lifetime for the purposes of calculating the IRR, the
requirement to take into account all relevant expected costs and benefits ‘over the
lifetime of the project’, laid down in the last sentence of paragraph 30 of the
IPCEI Communication, must be interpreted in the light of the factors to be taken
into consideration when carrying out the test of comparing the IRR, without aid,
with a benchmark. It must be noted that paragraph 30 of the IPCEI
Communication provides that the IRR must be compared with market indicators,
namely the sector- or firm-specific hurdle rate, and that normal rates of return
required by the beneficiary in other investment projects of a similar kind, as well
as cost of capital as a whole or returns commonly observed in the industry
concerned, may also be taken into account.
177 Furthermore, in the present case, as stated in paragraph 171 above, in order to
determine whether the IRR without aid was sufficient to achieve the minimum
level of profitability that would have been required by the market, it was
necessary to use the WACC. This is a rate which represents the cost of financing
from all sources (debt, equity) for a comparable project. It is common ground
between the main parties that the value of that rate reflects the minimum level of
profitability to be achieved in order for the project to be viable. It was calculated,
as is apparent from recitals 328 to 339 of the contested decision, by taking into
account market indicators (risk premium on debt, risk premium on equity, specific
risk premium, risk-free rate). Thus, since the test laid down in paragraph 30 of the
IPCEI Communication requires a determination of the minimum level of
profitability on the market for a comparable project, the Commission cannot be
criticised for having disregarded the IPCEI Communication by determining the
relevant period for the calculation of the IRR by taking into account the conduct
of investors on the market.
178 Similarly, the reference to the ‘lifetime of the project’ in the last sentence of
paragraph 30 of the IPCEI Communication cannot be interpreted as requiring the
Commission to examine whether the aid exceeds the minimum necessary for the
investment project in respect of the aided Fixed Link to be sufficiently profitable
over the lifetime of that infrastructure. That reference, which is intended to take
into account all the expected costs and benefits that have to be taken into
consideration, must be understood as referring to the economic lifetime of the
investment project and not the infrastructure from a technical perspective. It
follows that, in the circumstances of the present case, the Commission was
entitled to calculate the IRR from the Fixed Link project without aid, on the basis
of the economic lifetime of the investment project.
179 Second, as regards the period used to calculate the funding gap, it follows from
paragraph 31 of the IPCEI Communication that the cash flows must be discounted
on the basis of an appropriate discount factor reflecting the rate of return
necessary for the beneficiary to carry out the project, notably in view of the risks
36
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
involved. It follows that, as the Commission has stated, the purpose of the analysis
of the funding gap is to determine the extent to which the project could be
financed under market conditions. It follows from paragraph 5 of the IPCEI
Communication that aid granted for the deployment of important projects of
common European interest is intended to overcome the lack of financing available
on the market for the completion of such projects which require significant
participation by the public authorities. In the present case, for the calculation of
the funding gap, the WACC was also used to discount the cash flows of the
investment project. Since that rate was determined by taking into account market
parameters, the Commission cannot be criticised for having disregarded
paragraph 31 of the IPCEI Communication by taking into consideration, in order
to determine the relevant period for the purpose of calculating the funding gap, the
perception of investors on the market.
180 Third, as regards the argument of the applicants and of FSS that, in essence, the
period for the calculation of the IRR and the funding gap should correspond to the
‘period of the economic utilisation of the asset’ set out in point 99 of the
Guidelines on State aid to airports and airlines (OJ 2014 C 99, p. 3), it must be
held that, as the Commission states, those guidelines are not applicable in the
present case. In any event, in the context of the present case, a distinction must be
drawn between, on the one hand, the period of the economic utilisation of the
asset and, on the other hand, the lifetime of the asset, that is to say, the lifetime of
the infrastructure from a technical perspective. In that regard, it must be stated that
the 120-year lifetime referred to in recital 327 of the contested decision seems
more to refer to the lifetime of the asset from a technical perspective. Given the
evolution of modes of transport, it is difficult for an investor to predict whether it
would be possible to operate an infrastructure economically over such a long
period.
181 As regards the decisions on State aid in the airport sector relied on by the
applicants and as regards the decision on a railway tunnel relied on by FSS, it
should be noted that it is in the light of Article 107(3)(b) TFEU – and not of the
Commission’s previous practice – that it must be assessed whether or not aid
satisfies the conditions laid down by that provision for its application (see, to that
effect and by analogy, judgments of 21 July 2011,
Freistaat Sachsen and Land
Sachsen-Anhalt
v
Commission,
C-459/10 P, not published, EU:C:2011:515,
paragraph 38, and of 22 September 2020,
Austria
v
Commission,
C-594/18 P,
EU:C:2020:742, paragraph 25). In any event, it must be noted that it is apparent
from those decisions that the period used in those decisions in order to calculate
the funding gap was less than 40 years and that it was not necessarily dependent
on the duration of the concession awarded for the operation of the infrastructure
when the latter duration is long.
182 It follows from the foregoing considerations that, in order to determine the
relevant period for calculating the IRR and the funding gap, the Commission was
entitled to rely on the conduct of investors on the market. It follows that the
Commission cannot be criticised for not having calculated the IRR and the
37
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
funding gap on the basis of a period of 120 years corresponding to the estimated
lifetime of the project.
183 In the third place, it is necessary to ascertain whether the Commission made a
manifest error of assessment in using 40 years as the economic lifetime of the
investment in order to calculate the IRR and the funding gap.
184 In the present case, as stated in paragraph 170 above, in recital 327 of the
contested decision, the Commission explained why it would not be reasonable to
use a period of 120 years. Thus, since it was for the Commission to determine the
cost of financing, on the market, an investment comparable to that made for the
Fixed Link, the Commission took the view that it was appropriate to work on the
assumption that the operational period would be 40 years, which it considers to be
longer than the period used for other infrastructure projects in the ports and airport
sectors.
185 As regards the applicants’ argument that, in essence, the period of 40 years does
not allow certain future revenue to be taken into account, which has the effect of
artificially reducing the IRR and artificially increasing the funding gap, given the
uncertainties inherent in investments over a very long period, the Commission did
not make a manifest error of assessment by considering that, even taking into
account a longer period, the net effects on possible revenue beyond 40 years
would probably be limited. As the Commission submits in its defence, in order to
guard against the risks inherent in investments lasting beyond 40 years, an
investor would probably have required a higher return, which would have had the
effect of increasing the WACC and, consequently, of reducing the value of
discounted future revenue.
186 As regards the arguments of the applicants, ECSA, Trelleborg Hamn and VDR
that, in essence, the Commission made a manifest error of assessment in that it
used a period of 40 years to calculate the IRR and the funding gap, whereas a
period of 50 years was used in the Incentive studies for the assessment of the
socioeconomic return, a distinction must be drawn between the socioeconomic
return of a project and parameters such as the IRR and the funding gap, which
relate solely to the financial evaluation of a project. First, it should be noted, as the
main parties submit, that the socioeconomic return is the result of a
socioeconomic analysis of a project, carried out in order to assess the benefits of a
project for society, with the result that account is taken, in addition to the financial
parameters, of the positive and negative externalities of a project. Second, it
should be noted that, as the main parties submit, the IRR and the funding gap are
parameters, determined solely on the basis of the cash flows generated by the
project, which enable an investor to assess whether it is appropriate to invest in a
project. In view of the differences between the socioeconomic analysis and the
financial analysis of a project, the fact that the period used to assess the benefits of
the project for society is longer than that used to assess its financial feasibility
cannot render the results of each of those analyses implausible.
38
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
187 As regards the applicants’ argument that the period of 40 years is incorrect on the
ground that the Incentive studies show that, after a period of 50 years, the Fixed
Link would still have a residual value of EUR 11.7 billion or a high capital value,
so that, at the end of a period of 40 years, additional revenue could be generated or
the sale of the tunnel could generate a profit, it must be stated that those studies do
not refer to such a residual value. In response to the Court’s request, at the
hearing, for clarification in that regard, Trelleborg Hamn argued that it was a
residual value of DKK 11.7 billion and not EUR 11.7 billion, based on Femern’s
financial analysis of February 2016. It must be noted that the passage of that
financial analysis referred to by that intervener concerns stress tests and the
finding that the project could bear additional costs of DKK 11.7 billion.
Consequently, it must be held that the argument as to a residual value of
DKK 11.7 billion after a period of 50 years is not supported by any evidence.
Moreover, in order to justify a high residual value equivalent to the construction
costs, reference is made to the handbook for socioeconomic assessment in the
field of transport, drawn up in March 2015 by the Danish Ministry of Transport. It
must also be stated that the applicants, VDR, ECSA and Trelleborg Hamn have
not explained why a supposed high residual value after 50 years, determined in the
context of a socioeconomic analysis, would mean that the Commission made a
manifest error of assessment in using, in the financial analysis of a project, a
period of 40 years to calculate the IRR and the funding gap. In particular, no
information is provided to indicate that a market investor would take into account
the residual value after an operational period of 40 or 50 years in order to
determine the minimum return that would be required. In that regard, it should be
noted that it is apparent from recitals 337 and 338 of the contested decision that,
even over a period of 40 years, the level of uncertainty may constitute a difficulty
for determining certain components of the WACC, in particular the risk-free rate.
Therefore, over a period beyond 40 years, the even higher level of uncertainty
would probably have made the WACC determination too approximate to reflect
properly the cost of financing the project on the market.
188 It follows from the foregoing considerations that the applicants, FSS, VDR, ECSA
and Trelleborg Hamn have not established that the Commission made a manifest
error of assessment in relying on a period of 40 years to calculate the project’s
IRR and funding gap.
189 Therefore, there is no longer any need to rule on the arguments challenging the
calculation of the IRR that was made until 2100 as a precautionary measure.
190 Accordingly, the complaint challenging the periods used for the calculation of the
IRR (necessity of the aid) and for the calculation of the funding gap
(proportionality of the aid) must be rejected.
191 In the light of the foregoing considerations, the second part of the second plea
must be rejected in its entirety.
39
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
3.
The third part, alleging that the Commission was wrong to conclude that
the aid was proportionate
192 In the third part of the second plea, the applicants raise three complaints,
challenging, first, the temporal limitation of the aid, second, the funding gap and,
third, the aid amount.
(a)
The first complaint, challenging the temporal limitation of the aid
193 The applicants, ECSA, Trelleborg Hamn and VDR consider that the Commission
made a manifest error of assessment with regard to the proportionality of the aid at
issue, on the ground that the aid is not limited in time and, in any event, the period
of 16 years after the opening of the Fixed Link, used in the contested decision, is
too long.
194 The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
195 In that regard, it should be noted that it is apparent from paragraph 36 of the
IPCEI Communication that the choice of the aid instrument must be made with a
view to the market failure or other important systemic failures which it seeks to
address, and that, where the underlying problem is lack of access to finance,
Member States should normally resort to aid in the form of liquidity support, such
as a loan or guarantee. With regard to aid in the form of a loan or guarantee,
footnote 27 to paragraph 36 of the IPCEI Communication states that aid in the
form of guarantees must be limited in time, and aid in the form of loans must be
subject to repayment periods.
196 In the present case, in recital 348 of the contested decision, the Commission stated
that the Danish authorities had ensured that Femern would not adopt State loans
and State guarantees, which, together, would exceed a maximum guaranteed
amount of DKK 69.3 billion (approximately EUR 9.3 billion), and that those loans
and guarantees are strictly limited to the planning and construction costs of the
Fixed Link. In addition, according to the alternative funding gap model, submitted
by the Danish authorities during the formal investigation procedure, the
Commission found, in recital 349 of the contested decision, that, 16 years after the
start of operation, all loans with a State guarantee would be terminated and all
State loans obtained would be repaid. According to the Commission, as is
apparent from recital 350 of the contested decision, the resulting aid is equal to the
funding gap of DKK 12.046 billion (approximately EUR 1.615 billion).
Moreover, it is apparent from recital 351 of the contested decision that, since it
cannot be ruled out that the funding gap may be overestimated as a result of the
inclusion of a reserve budget, the Danish authorities will have to recalculate the
funding gap at the latest five years after the start of operation, and that, if the
funding gap were below what was anticipated, the maximum guaranteed amount
would be reduced to DKK 66.1 billion (approximately EUR 8.9 billion) and the
40
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
maximum guarantee period would be reduced to 11 years from the start of
operation.
197 In the first place, as regards the arguments that the duration of the aid is not
limited in time, first, the Court must reject the argument of the applicants, ECSA,
Trelleborg Hamn and VDR that, in essence, the Commission provided no
indication as to the point in time when the aid was granted. As the Commission
submits, the dates on which the three individual aids were successively granted to
Femern are set out in recital 259 of the contested decision. In addition, such an
argument is irrelevant for the purpose of claiming that the Commission
disregarded the requirement under paragraph 36 of the IPCEI Communication,
referred to in paragraph 195 above, according to which aid in the form of
guarantees must be limited in time and aid in the form of loans must be subject to
repayment periods. Contrary to what the applicants claim, the IPCEI
Communication does not require precise dates to be determined, and consequently
it is not necessary to know precisely the point in time when the aid was granted.
198 Second, as regards the applicants’ argument that, in essence, the aid is not limited
in time on the ground that it is not possible to determine the end date of the aid
because the date upon which the Fixed Link will be opened is uncertain, it must be
noted that the Commission ensured, in recitals 348 to 351 of the contested
decision, that temporal limits would be set for the grant of State loans and State
guarantees.
199 As stated in recital 349 of the contested decision, all loans with a guarantee must
have been terminated at the latest 16 years after the start of operation of the Fixed
Link and all State loans must have been repaid, and no guarantee will be provided
after the actual debt is repaid if the repayment period of that debt is less than
16 years.
200 Moreover, the State loans and State guarantees are strictly limited to financing the
costs of planning and constructing the Fixed Link and the Danish authorities are
not authorised to grant Femern such loans and guarantees for an amount
exceeding the maximum guaranteed amount of DKK 69.3 billion (approximately
EUR 9.3 billion), and that amount also includes interest on the debt taken on to
finance the planning and construction of the Fixed Link. Therefore, as the
Commission stated, any delays in the full opening of the Fixed Link would have
the effect of increasing the debt taken on to finance the planning and construction
of the Fixed Link, which is strictly capped by the maximum guaranteed amount
and the repayment period of 16 years after the opening of the Fixed Link. It
follows that, should Femern need, in order to finalise the construction of the Fixed
Link, State loans or State guarantees for a combined amount that exceeds the
maximum guaranteed amount, the Danish authorities would be required to notify
such additional financing which would not be covered by the declaration of
compatibility in the contested decision. It follows that the applicants cannot claim
that it would be in Femern’s interest to delay the full operation of the Fixed Link
in order to extend the duration of the aid.
41
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
201 In addition, it must be noted that, since the funding gap might be overestimated
because of the inclusion of a reserve budget in the maximum guaranteed amount,
the Commission required, in recital 351 of the contested decision, that the Danish
authorities recalculate the funding gap at the latest five years after the start of
operation of the Fixed Link. If the funding gap were to have been overestimated,
the maximum guaranteed amount could be reduced to DKK 66.1 billion
(approximately EUR 8.9 billion) and the maximum guaranteed period could be
reduced to 11 years from the start of operation.
202 Contrary to what the applicants claim, the rules governing how the duration of the
State loans and the State guarantees is limited in the contested decision does not
disregard the grounds of the judgment of 13 December 2018,
Scandlines Danmark
and Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), because the end date of the aid is not sufficiently precise.
203 In that regard, it should be noted at the outset that, in the judgment of
13 December 2018, Scandlines
Danmark and Scandlines Deutschland
v
Commission
(T-630/15, not published, EU:T:2018:942), the Court did not hold
that the Commission had made a manifest error of assessment in the examination
of the proportionality of the aid, but that it should have initiated the formal
investigation procedure on account of serious difficulties in the assessment of the
proportionality of the aid. In particular, as regards the duration of the guarantees,
the Court considered that, in view of the partially indeterminate nature of their
object and the extremely long and indeterminate, or indeed unforeseeable,
duration of the debt repayment period, the Commission should have questioned
the proportionality of the aid at issue.
204 It must be noted that the applicants misunderstand the scope of the incidental
finding concerning the date of opening of the Fixed Link, made in paragraph 230
of the judgment of 13 December 2018,
Scandlines Danmark and Scandlines
Deutschland
v
Commission
(T-630/15, not published, EU:T:2018:942). It is true
that the Court referred to the date of the opening of the Fixed Link as being
uncertain. However, it follows from a reading of paragraphs 230 to 233 of that
judgment that that incidental finding was only one of the factors taken into
account in order to conclude, in circumstances differing from those of the present
case, that the Commission should have initiated the formal investigation
procedure. As regards the partially indeterminate nature of the object of the
guarantees, the Court stated that the guarantees at issue covered the debt taken on
for the planning, construction and operation of the Fixed Link, but that those
guarantees did not relate to a precise cost. As regards the extremely long and
indeterminate, or indeed unforeseeable, debt repayment period, the Court stated
that the Danish authorities could grant new guarantees for a period of 55 years
from the date on which the Fixed Link is opened. Thus, the Court found that the
effect of the guarantees extended well beyond the 55-year period from the opening
of the Fixed Link, namely until the loans with a State guarantee are repaid.
42
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
205 It must be stated that the detailed rules for limiting the duration of the State loans
and the State guarantees, as defined in the contested decision, cannot be compared
to those which governed the grant of guarantees in the 2015 Construction
Decision. As is apparent from recitals 348 to 351 of the contested decision, the
Commission ensured that the object of the State loans and the State guarantees
would be strictly limited, including as regards the maximum amount of debt that
could be guaranteed. It is also required that, at the latest 16 years after the start of
operation of the Fixed Link, all loans with a guarantee must be terminated and all
State loans repaid. Moreover, should the funding gap have been overestimated,
both the maximum guaranteed amount and the repayment period of the loans and
guarantees are to be reduced.
206 It follows that the applicants cannot complain that the Commission disregarded
the requirement under paragraph 36 of the IPCEI Communication that the aid be
limited in time.
207 In the second place, it is necessary to examine whether, as the applicants, ECSA,
Trelleborg Hamn and VDR claim, the Commission made a manifest error of
assessment on the ground that the 16-year period from the opening of the Fixed
Link is too long in that it goes beyond the point in time when Femern will be able,
on the basis of its cash flow, to finance itself on the market, with the result that,
beyond that point in time, the aid constitutes operating aid that is incompatible
with the internal market.
208 It should be noted that that line of argument is based on an isolated reading of
paragraph 242 of the judgment of 13 December 2018,
Scandlines Danmark and
Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), in which the Court held that the aid should expire at the point in
time when the beneficiary would be able, on the basis of its cash flow, to borrow
on the open market without the support of State guarantees or State loans. In that
regard, the Court stated that that point was normally reached when the amount of
the beneficiary’s debt had reached a level at which its income was likely to exceed
operating costs and debt repayments under normal market conditions, and
therefore before the debt had been repaid in full. Therefore, according to the
Court, aid in excess of that level could be regarded as operating aid.
209 Paragraph 242 of the judgment of 13 December 2018,
Scandlines Danmark and
Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), cannot be read or interpreted independently of the context in
which that case was brought before the Court, namely, as follows from
paragraph 240 of that judgment, the context of the measures at issue granted to
Femern which covered not only the debt associated with the planning and
construction of the Fixed Link, but also the debt relating to its operation.
Therefore, in paragraph 241 of that judgment, the Court held that, as the aid at
issue covered the operating costs of the Fixed Link, it cannot be ruled out that, to
some extent, it may constitute operating aid which is intended to release an
undertaking from the costs which it would normally have to bear in the day-to-day
43
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
management of its activities, which is why the Court laid down the criterion relied
on by the applicants, ECSA, Trelleborg Hamn and VDR.
210 It must be stated that, unlike the 2015 Construction Decision which the Court
annulled by the judgment of 13 December 2018,
Scandlines Danmark and
Scandlines Deutschland
v
Commission
(T-630/15, not published,
EU:T:2018:942), it is apparent in particular from recital 348 of the contested
decision that the State loans and State guarantees are strictly limited to the
financing needed for the costs incurred during the phases of planning and
constructing the Fixed Link. It follows that, in the absence of loans or guarantees
capable of covering operating costs, the Commission was not required to limit the
duration of the aid to the point in time when the beneficiary would be able, on the
basis of its cash flow, to borrow on the competitive market without having State
guarantees or loans.
211 In any event, the applicants, ECSA, Trelleborg Hamn and VDR have not adduced
any evidence to establish that the 16-year limit from the opening of the Fixed Link
is manifestly incorrect. The applicants have merely submitted that the operating
revenue of the entities responsible for the construction and operation of the Great
Belt and Øresund Belt fixed links exceeded the amount of the operating costs and
debt repayment costs from the fourth or fifth year from the opening of those links.
Apart from the fact that that assertion is not supported by probative evidence, the
applicants have also failed to demonstrate that Femern is in a situation that is
comparable to that of the entities responsible for the construction and operation of
the Great Belt and Øresund Belt fixed links, in particular as regards the
remuneration required for the State loans and State guarantees or the fact that the
entities responsible for those links were able to receive State guarantees capable of
covering operating costs.
212 It must therefore be held that the applicants, ECSA, Trelleborg Hamn and VDR
have not demonstrated that the Commission made a manifest error of assessment
in limiting the duration of the aid to a period of 16 years from the opening of the
Fixed Link.
213 Accordingly, the first complaint, challenging the temporal limitation of the aid,
must be rejected.
(b)
The second complaint, challenging the funding gap
214 The second complaint in the third part of the second plea is subdivided into three
sub-complaints, challenging, first, the revenues taken into account in the
calculation of the funding gap, second, the costs taken into account in the
calculation of the funding gap and, third, the period used for the purposes of
calculating the funding gap.
44
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
215 Since the third sub-complaint has already been examined in paragraphs 168 to 190
above, in the context of the third complaint in the second part of the second plea,
the merits of the first and second sub-complaints remain to be examined.
(1)
The first sub-complaint, challenging the revenue
216 The applicants, DFA and Rederi Nordö-Link submit that, for the calculation of the
funding gap, the Commission underestimated Femern’s revenues in order to
increase artificially the funding gap.
217 The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
218 In the present case, as regards the revenues from the Fixed Link, the Commission
considered, in recital 322 of the contested decision, that the road traffic forecasts
were reasonable, in particular in so far as those forecasts take into account
redistribution of traffic linked to the reduction of the Great Belt fixed link toll and
continued competition from ferry services. In that regard, it stated that a
reasonable investor would, in its financial analysis, take into account a continued
ferry service, and considers a one-hour ferry service to be appropriate.
219 In addition, in recital 323 of the contested decision, concerning the assumed
prices, the Commission stated that operating revenues largely exceeded operating
costs and that prices could not be required to compensate all the costs, including
construction costs. However, it stated that the prices assumed in the funding gap
model could not be artificially low. In the present case, it observed that the Danish
legislation had laid down the principle that the price level for road traffic was
expected to be at the level of the ferry prices for Rødby-Puttgarden in 2007,
adjusted by the general increase in prices up to the time of opening. In that regard,
the Commission stated that the traffic forecasts had been developed on the basis of
those prices and that the establishment of a differentiated price structure would
have a limited effect on revenues. The Commission therefore considered that the
assumed road traffic revenues were plausible and appropriate. As regards railway
revenues, in recital 324 of the contested decision, the Commission considered that
the basis for the calculation of those revenues was reasonable.
220 It must be stated that, by the present sub-complaint, the applicants, DFA and
Rederi Nordö-Link merely dispute the fact that, in order to find that road traffic
revenues could be regarded as plausible and appropriate, the Commission
accepted the assumption of prices at the level of the ferry prices for Rødby-
Puttgarden in 2007, adjusted for inflation.
221 In that regard, it must be noted that, according to paragraph 31 of the IPCEI
Communication, the funding gap refers to the difference between the positive and
negative cash flows over the lifetime of the investment, discounted to their current
value on the basis of an appropriate discount factor reflecting the rate of return
45
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
necessary for the beneficiary to carry out the project notably in view of the risks
involved.
222 In addition, since the funding gap is intended to determine the extent to which the
project could be financed under market conditions, in the assessment of revenues,
the Commission, DFA and Rederi Nordö-Link rightly consider that account must
be taken of the conduct, on the market, of a private investor who as far as possible
would seek to ensure that revenue is established at a level that would enable
investment costs to be recovered as much as possible.
223 It is in the light of those considerations that it is necessary to examine the
arguments raised by the applicants, DFA and Rederi Nordö-Link.
224 First, as regards the applicants’ argument that, in essence, the Commission made a
manifest error of assessment in accepting that Femern’s revenues did not
compensate all of its costs, including the costs of constructing the Fixed Link, it
should be noted that paragraph 31 of the IPCEI Communication cannot be
interpreted as requiring that the revenues cover all of the costs incurred by the aid
beneficiary. As the Commission stated in recital 323 of the contested decision, if
revenues were required to be set at a level that would cover the full construction
and operating costs, there would be no funding gap, with the result that no aid
could be authorised even though the aid was necessary for the investment project
to be carried out.
225 Furthermore, as the Commission rightly states, the fact that prices are higher does
not automatically lead to an increase in revenue because of the elasticity of
demand in relation to price. In that regard, it must be noted that the applicants,
DFA and Rederi Nordö-Link do not dispute the finding made in recital 323 of the
contested decision to the effect that it is apparent from the 2016 financial analysis
that a differentiated price structure would have only a relatively limited impact on
overall revenues.
226 Moreover, the applicants acknowledge in their reply that higher prices do not
automatically lead to an increase in revenues because of competition from other
operators on the market. Contrary to what the applicants claim, that does not mean
that the economic model chosen for the Fixed Link is inappropriate, but confirms
that the grant of aid is necessary for such a project to be carried out.
227 Second, it must be stated that the applicants, DFA and Rederi Nordö-Link have
not adduced any evidence to establish that it would have been possible to achieve
higher revenues by setting higher prices for road traffic.
228 It should be noted, first of all, that the argument put forward by DFA and Rederi
Nordö-Link that, in essence, the prices for the use of the Fixed Link should be
higher than the prices for ferry services on the route between Rødby and
Puttgarden on the ground that the Fixed Link provides a service that is superior to
those provided by the ferry operators is not supported by any evidence. Those
interveners have not referred to any evidence relating to the prices charged by the
46
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
current ferry operator on the route between Rødby and Puttgarden. Therefore,
DFA and Rederi Nordö-Link cannot claim that the prices for the use of the Fixed
Link are in fact equal to or lower than those charged by the current ferry operator
on that route.
229 Next, it must be stated that the example of the tariffs charged by Eurotunnel,
relied on by DFA and Rederi Nordö-Link, is not supported by any evidence.
Furthermore, in so far as it concerns the Channel Tunnel fixed link, that example
cannot be relevant, since it is apparent from the information in the file that that
fixed link is intended only for railway traffic. It must be noted that neither the
applicants nor those interveners dispute the Commission’s finding in recital 324 of
the contested decision that the basis for the calculation of the railway operating
revenues is reasonable.
230 Lastly, as regards the example of the Rio-Antirrio (Greece) bridge, the fact that
the prices for road traffic over the fixed link are higher than those for ferry
services cannot be relevant where there are no contextual factors capable of
establishing that that fixed link’s situation is, at least to some extent, comparable
to the situation of the Fehmarn Belt fixed link. In the absence of data relating to
the construction costs, of information concerning the way in which the Rio-
Antirrio bridge is financed or of any price framework set by the public authorities
for use of that fixed link, no conclusion can be drawn from the difference between
the prices charged for road traffic using that bridge and the prices envisaged for
use of the road part of the Fixed Link.
231 Third, as regards the argument put forward by DFA and Rederi Nordö-Link that,
in essence, the Commission cannot authorise aid where the beneficiary’s revenues
are lower than its costs, to the detriment of its competitors, it should be noted that
taking into account the negative effects of aid on competitors is irrelevant for the
purposes of assessing the funding gap. It follows that that argument is ineffective.
In any event, such an argument is unfounded for the same reasons as those set out
in paragraphs 224 and 225 above.
232 Fourth, the argument put forward by DFA at the hearing, by which the
Commission is criticised for having accepted that revenues are not determined by
taking into account the prospect of maximising profits, cannot, in any event,
succeed.
233 That line of argument based on the finding that Femern cannot itself determine the
tariffs for use of the Fixed Link on the ground that the latter is not intended to be
operated in order to produce a maximum return, but addresses concerns relating in
particular to transport policy, cannot suffice to establish that the Commission
made a manifest error of assessment where there is no other element from which it
could be concluded that the revenues used to calculate the funding gap are
implausible.
47
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
234 Moreover, as the Commission stated at the hearing, where the public authorities
decide to regulate charges for use of an infrastructure for the purposes of
implementing transport policy in order to take account of the price that future
users would be prepared to pay, a private operator who is responsible for the
operation of such an infrastructure, as with certain motorways the prices of which
are regulated, cannot disregard, in the assessment of revenues for the calculation
of the funding gap, the fact that prices are regulated by the public authorities.
235 It follows from the foregoing considerations that the applicants, DFA and Rederi
Nordö-Link have not demonstrated that the Commission made a manifest error of
assessment consisting in an underestimation of the revenues taken into account in
the calculation of the funding gap.
236 Accordingly, the first sub-complaint, challenging the revenues taken into account
in the calculation of the funding gap, must be rejected.
(2)
The second sub-complaint, challenging the costs
237 The applicants, DFA and Rederi Nordö-Link submit that the Commission, for the
calculation of the funding gap, erred by taking into account the costs of
refinancing loans.
238 The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
239 In that regard, it should be noted that, according to settled case-law, operating aid
intended to maintain the status quo or to release an undertaking from costs which
it would normally have had to bear in its day-to-day management or normal
activities cannot, in principle, be considered compatible with the internal market
(see, to that effect and by analogy, judgments of 6 November 1990,
Italy
v
Commission,
C-86/89, EU:C:1990:373, paragraph 18; of 22 September 2020,
Austria
v
Commission,
C-594/18 P, EU:C:2020:742, paragraph 119; and of
12 July 2018,
Austria
v
Commission,
T-356/15, EU:T:2018:439, paragraph 579).
240 In addition, as stated in paragraph 221 above, it is apparent from paragraph 31 of
the IPCEI Communication that the maximum aid level will be determined with
regard to the identified funding gap in relation to the eligible costs. As regards
eligible costs under aid measures for an important project of common European
interest, point (h) of the annex to the IPCEI Communication specifies that costs
other than those referred to in points (a) to (g) of that annex may be accepted if
justified and where they are inextricably linked to the realisation of the project, to
the exclusion of operating costs not covered by point (g), which concerns aid to a
project of first industrial deployment.
241 In the present case, first, in recital 320 of the contested decision, the Commission
stated that the eligible costs were restricted to the project’s construction costs,
which include planning costs and costs for promotion, marketing and information.
48
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
Second, in recitals 325 and 326 of the contested decision, it stated that the
question of whether operating costs could be included in the calculation of the
funding gap differed from the question of whether operating aid was granted. It
indicated that paragraph 31 of the IPCEI Communication referred to the
difference between positive and negative cash flows when defining the funding
gap, and that it is inherent in the logic of investment decision-making to compare,
ex ante,
investment costs against future operating revenues and costs. In that
regard, the Commission also stated that investors typically did not take a positive
investment decision as long as that comparison resulted in a gap or a negative net
present value (NPV). Furthermore, the Commission stated that that method was
confirmed by the compatibility criteria set out in Commission Regulation (EU)
No 651/2014 of 17 June 2014 declaring certain categories of aid compatible with
the internal market in application of Articles 107 and 108 [TFEU] (OJ 2014
L 187, p. 1).
242 In the first place, it should be noted that the pleadings of the applicants, DFA and
Rederi Nordö-Link do not contain any substantiated arguments in support of the
assertion that the Commission erred in including operating costs in the negative
cash flows of the investment project. In particular, no argument is expressly raised
to call into question the merits of the Commission’s findings in recitals 325 and
326 of the contested decision.
243 When questioned by the Court at the hearing in order to clarify their arguments,
the applicants stated that the judgment of 19 September 2018,
HH Ferries and
Others
v
Commission
(T-68/15, EU:T:2018:563), prohibited the inclusion of
operating costs in the funding gap. The applicants also stated that that prohibition
followed from the annex to the IPCEI Communication, which excludes operating
costs from the eligible costs. In addition, Rederi Nordö-Link submits that taking
into account operating costs in the funding gap amounts to authorising operating
aid and to artificially increasing the funding gap.
244 First, it should be noted that, as the Commission submits, the inclusion of
operating costs in the negative cash flows of the investment project in order to
calculate the funding gap does not result in the grant of operating aid. As is
apparent from recital 323 of the contested decision, the operating revenues which,
correlatively, should also be taken into account under the positive cash flows
largely exceed operating costs. Therefore, Rederi Nordö-Link cannot claim that
the inclusion of operating costs in the funding gap would result in the grant of
operating aid.
245 Second, it must be stated that the argument put forward by DFA and Rederi
Nordö-Link that the inclusion of operating costs in the calculation of the funding
gap has the effect of artificially increasing that gap cannot suffice to conclude that
the Commission disregarded paragraph 31 of the IPCEI Communication by
including operating costs in the calculation of the funding gap. As stated in
paragraph 241 above, the Commission explained, in recital 326 of the contested
decision, the reasons why the operating costs formed an integral part of the
49
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
funding gap analysis. It follows that, in the absence of evidence capable of calling
into question the validity of those explanations, that argument cannot succeed.
246 As regards the judgment of 19 September 2018,
HH Ferries and Others
v
Commission
(T-68/15, EU:T:2018:563), the Court was not called upon to interpret
the concept of ‘funding gap’ within the meaning of paragraph 31 of the IPCEI
Communication. It follows that the applicants are not justified in claiming that
that judgment could be interpreted as prohibiting the inclusion of operating costs
in the calculation of the funding gap.
247 Consequently, it must be held that the applicants, DFA and Rederi Nordö-Link
have not demonstrated that the Commission’s calculation of the funding gap
disregarded paragraph 31 of the IPCEI Communication as a result of the inclusion
of operating costs in the negative cash flows of the investment project.
248 In the second place, it should be noted that the applicants, DFA and Rederi Nordö-
Link also rely on the judgment of 19 September 2018,
HH Ferries and Others
v
Commission
(T-68/15, EU:T:2018:563), in order to claim that the Commission
erred in finding, in recital 294 of the contested decision, that the guarantees for
refinanced loans relating to planning and construction costs did not constitute
operating aid.
249 In that regard, it should be noted that it follows from the judgment of
19 September 2018,
HH Ferries and Others
v
Commission
(T-68/15,
EU:T:2018:563), and in particular from paragraphs 107, 108 and 111 thereof, that
it cannot be ruled out that State guarantees covering the operating costs of the
beneficiary of the aid may constitute operating aid. However, it does not follow
that guarantees such as those granted for refinanced loans relating to planning and
construction costs, and not operating costs, constitute such operating aid.
250 It must be stated that, as is apparent from recitals 292 and 293 of the contested
decision, the Danish authorities limited the provision of State loans and State
guarantees to the financing needed for the costs incurred during the planning and
construction phases, excluding operating costs. In the light of that limitation, the
Commission was entitled to take the view that the aid in question was investment
aid, and that conclusion cannot be called into question, as the applicants, DFA and
Rederi Nordö-Link claim, by the findings made by the Court in the judgment of
19 September 2018,
HH Ferries and Others
v
Commission
(T-68/15,
EU:T:2018:563).
251 As regards the argument put forward by DFA and Rederi Nordö-Link that Femern
benefits from operating aid on the ground that the aid measures in its favour may
continue for a period of 16 years after the full opening of the Fixed Link, whereas
that period goes beyond the point in time when that entity will be able, on the
basis of its cash flows, to finance itself on the competitive market without aid, it
should be noted that that argument overlaps with the argument already examined
50
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
in paragraphs 208 to 212 above and must, therefore, be rejected for the same
reasons.
252 In the light of the foregoing considerations, it must be held that the Commission
did not err in finding that the refinancing of loans relating to the planning and
construction costs did not constitute operating aid.
253 Accordingly, the second sub-complaint, challenging the costs taken into account
in the calculation of the funding gap, must be rejected.
(c)
The third complaint, challenging the aid amount
254 The applicants, FSS, DFA and Rederi Nordö-Link submit that the Commission
made manifest errors of assessment in the calculation of the aid amount.
255 The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
256 In the first place, it is necessary to ascertain whether, as the applicants and DFA
submit, since Femern does not have the ability to repay its loans, as, they claim, is
apparent from the 2001 commercial interest report, in accordance with point 4.1 of
the Guarantee Notice, the aid amount should correspond, contrary to what the
Commission found, to the value of all loans covered by the State guarantees and
of all State loans.
257 In that regard, it should be noted that, according to point (a) of the third paragraph
of point 4.1 of the Guarantee Notice, ‘for companies in difficulty, a market
guarantor, if any, would, at the time the guarantee is granted charge a high
premium given the expected rate of default[; if] the likelihood that the borrower
will not be able to repay the loan becomes particularly high, this market rate may
not exist and in exceptional circumstances the aid element of the guarantee may
turn out to be as high as the amount effectively covered by that guarantee’.
258 Thus, it follows from point (a) of the third paragraph of point 4.1 of the Guarantee
Notice that it is only where a company is in difficulty and in exceptional
circumstances that the aid element of a guarantee is equivalent to the total amount
of the loans covered by the guarantee. Given the far-reaching implications of such
an approach, the possibility of calculating the benefit from a State guarantee as
being equal to the entire amount of the guaranteed loan cannot be justified merely
because the beneficiary undertaking is in difficulty. Thus, the Commission may
use that approach only in exceptional circumstances and only if the company in
difficulty is unable, through its own resources, to repay the loan covered by the
guarantee.
259 In the present case, in recital 346 of the contested decision, the Commission found
that the aid element did not have to equal the full amounts covered by the State
loans and the loans with State guarantees, on the ground that Femern’s situation
51
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
did not come under the exceptional circumstances referred to in point (a) of the
third paragraph of point 4.1 of the Guarantee Notice.
260 It must be stated that the applicants and DFA have not adduced any evidence to
support the view that Femern is an undertaking in difficulty within the meaning of
the Guidelines on State aid for rescuing and restructuring non-financial
undertakings in difficulty, or that that undertaking would be unable to repay the
loans covered by the debt taken on to cover the planning and construction costs.
261 To support their line of argument, the applicants and DFA rely solely on the 2001
commercial interest report, from which it is apparent that the Fixed Link project
could not be carried out by the private sector without substantial public support.
While such a factor may be relevant for determining whether the State loans and
the State guarantees granted to Femern constitute aid within the meaning of
Article 107(1) TFEU or to establish that such a project cannot be carried out
without aid, it is not sufficient to establish that Femern is an undertaking in
difficulty which is unable to repay, at the stage of the Fixed Link being in
operation, the debt taken on to cover the planning and construction costs.
262 Accordingly, it must be held that the applicants and DFA have not demonstrated
that the Commission erred in finding that the aid amount cannot equal the full
amounts covered by the State loans and loans with State guarantees.
263 In the second place, as regards the applicants’ argument that Femern is not paying
the premium set out in recitals 342 and 343 of the contested decision, it should be
noted that, in support of that argument, the applicants rely only on elements
subsequent to the adoption of the contested decision, namely a statement by the
Danish Minister for Transport of 24 April 2020 and a proposal of 5 December
2020 regarding an amendment to the 2015 Construction Law. In that regard, it
must be noted that, according to settled case-law, the legality of a Commission
decision on State aid is to be assessed in the light of the information available to
the Commission when that decision was adopted (judgments of 10 July 1986,
Belgium
v
Commission,
234/84, EU:C:1986:302, paragraph 16, and of 12 July
2018,
Austria
v
Commission,
T-356/15, EU:T:2018:439, paragraph 333). It
follows that that argument by the applicants cannot call into question the legality
of the contested decision.
264 In the third place, it is necessary to examine the line of argument by which the
applicants, FSS and Rederi Nordö-Link submit, in essence, that it is impossible
for the result of the calculation of the aid amount to correspond to that of the
funding gap.
265 In the present case, in recital 342 of the contested decision, the Commission first
of all set out the methodology used by the Danish authorities to calculate the aid
amount. The Commission stated that that method was based on an approach
similar to that set out in point 4.2 of the Guarantee Notice, which provides that,
where no market price for the guarantee is available, ‘the aid element should be
52
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
calculated in the same way as the grant equivalent of a soft loan, namely as the
difference between the specific market interest rate this company would have
borne without the guarantee and the interest rate obtained by means of the State
guarantee after any premiums paid have been taken into account’. The
Commission also stated that the Danish authorities, when calculating the aid
amount, had not distinguished between the value of aid associated with the State
loans and the value of aid associated with the State guarantees, and therefore the
aid elements resulting from the State guarantees and from the State loans were
therefore calculated in the same way. In addition, the Commission stated that the
Danish authorities had determined the yearly aid element by taking the difference
between the WACC that a market investor would be expected to require (5.59%)
and the risk-free rate (1.5%) adjusted for the premium that Femern was required to
pay to the Danish State, multiplied by the sum of outstanding guaranteed debt and
outstanding State debt. The Commission set out, in recitals 343 to 345 of the
contested decision, the reasons why it considered that method to be appropriate.
266 Next, in recital 347 of the contested decision, it explained the components of
Femern’s effective debt, namely that it reflects the accumulated amount of money
spent to cover planning and construction costs, interest payments and own costs,
from which the amount of paid-in equity and financing received from the
European Union must be deducted. It also stated that Femern’s net debt built up
during the construction phase was expected to reach its maximum in the first year
of operation and that that net debt will gradually decrease during the operational
phase with the free cash flow of the project. In recitals 348 and 349 of the
contested decision, the Commission indicated the other parameters taken into
account in the calculation of the aid amount, namely the maximum guaranteed
amount and the maximum guaranteed period. On the basis of those elements, in
recital 350 of the contested decision, the Commission calculated the aid amount as
being DKK 12.046 billion (approximately EUR 1.615 billion). In that regard, it
stated that the aid was the discounted value using the WACC as the discount rate.
It also stated that that calculation included capital injections and aid associated
with State loans and State guarantees, and that the calculation of the aid amount
was based upon an increase of the premium from 0.15% to 2%.
267 It should be noted that, in their pleadings, the applicants, FSS and Rederi Nordö-
Link do not dispute either the methodology used to calculate the aid amount or the
parameters used to calculate the aid amount, namely the maximum guaranteed
amount, the WACC and the risk-free rate adjusted according to the premium.
Furthermore, as follows from paragraph 212 above, the applicants have not
demonstrated that the Commission made a manifest error of assessment in
limiting the duration of the aid to a period of 16 years from the opening of the
Fixed Link. The applicants, FSS and Rederi Nordö-Link merely claim that,
because of differences in the manner in which the funding gap and the aid amount
are calculated, it is mathematically impossible to achieve the same result.
268 It must be noted that, in recital 318 of the contested decision, the Commission
explained the relationship between the aid amount and the funding gap by stating
53
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
that ‘the aid amount is directly linked to the underlying assumptions of the
funding gap model, not only as a consequence of the limitation of the aid amount
to the funding gap level but also due to the fact that the level of the debt, and thus
the level of the aid amount, depends on factors such as the overall construction
cost and the interest rate assumed’.
269 Furthermore, as the Commission has submitted, since the funding gap is the
funding which is missing for the investment to be carried out, it must be held that
it is not unusual for the amount of aid to correspond to that of the funding gap.
270 It follows that the applicants, FSS and Rederi Nordö-Link are not justified in
claiming that it is impossible for the aid amount to correspond to the amount of
the funding gap.
271 As regards Rederi Nordö-Link’s complaint that aid amount was calculated in
order to ensure that that amount was the same as the funding gap, it should be
noted that the Danish authorities cannot be criticised for having calibrated the
various parameters used to calculate the aid amount, in particular the maximum
guaranteed amount and the premium applicable to the risk-free rate and the
duration of the aid, in order to ensure that the aid amount corresponded to the
funding gap which constitutes the maximum aid ceiling that may be authorised.
272 As regards FSS’s argument which, in essence, criticises the Commission for not
having calculated the aid amount, it must be noted that the fact that the details of
that calculation do not appear in the contested decision does not mean that the
Commission did not calculate the aid amount in order to arrive at the result
indicated in recital 350 of the contested decision.
273 Furthermore, it must be noted that the statement of reasons for a measure adopted
by the Commission must enable the persons concerned to ascertain the reasons for
the measure so that they can defend their rights and ascertain whether or not the
measure is well founded and so that the EU judicature can exercise its power of
review. It is not necessary for the statement of reasons to go into all the relevant
facts and points of law, since the question whether the statement of reasons meets
the requirements of Article 296 TFEU must be assessed with regard not only to its
wording but also to its context and to all the legal rules governing the matter in
question (judgments of 15 June 2005,
Corsica Ferries France
v
Commission,
T-349/03, EU:T:2005:221, paragraphs 62 and 63; of 16 October 2014,
Eurallumina
v
Commission,
T-308/11, not published, EU:T:2014:894,
paragraph 44; and of 6 May 2019,
Scor
v
Commission,
T-135/17, not published,
EU:T:2019:287, paragraph 80). In the present case, since, in recitals 342 to 350 of
the contested decision, the Commission set out both the method used to calculate
the aid and the parameters taken into account in order to calculate the aid amount,
the Commission cannot be accused of having failed to comply with the obligation
to state reasons.
54
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
274 In the fourth place, as regards the applicants’ argument that, in essence, Femern
received an economic advantage not taken into account in the aid amount, on the
ground that the construction and operation of the Fixed Link were awarded to it
without a tendering procedure taking place, suffice it to note that the applicants
have not set out the reasons why obtaining a right to construct and operate without
a tendering procedure taking place is likely to increase the aid amount. It follows
that, without it being necessary to rule on the admissibility of that argument raised
for the first time in their observations on Rederi Nordö-Link’s statement in
intervention, that argument must be rejected as unsubstantiated.
275 In the light of the foregoing considerations, the third complaint, challenging the
aid amount, must be rejected.
276 Accordingly, the third part of the second plea must be rejected in its entirety.
4.
The fourth part, challenging the analysis of the prevention of undue
distortions of competition and the balancing test
277 The applicants, supported by FSS, DFA, Rederi Nordö-Link, ECSA, Trelleborg
Hamn, Aktionsbündnis, NABU and VDR, submit that the Commission erred in
concluding that the negative effects of the Fixed Link on competition were not
capable of offsetting its positive effects.
278 The Commission, supported by the Kingdom of Denmark, disputes that line of
argument.
279 In that regard, according to paragraph 41 of the IPCEI Communication, for the aid
to be compatible with the internal market, the negative effects of the aid in terms
of distortions of competition and impact on trade between Member States must be
limited and outweighed by the positive effects in terms of contribution to the
objective of the common European interest. Paragraph 42 of that communication
states that, in the assessment of the negative effects of the aid, the Commission
will focus its analysis on the foreseeable impact the aid may have on competition
between undertakings in the product markets concerned, including up- or
downstream markets, and on the risk of overcapacity. In addition, according to
paragraph 43 of the IPCEI Communication, the Commission is required to assess
the risk of market foreclosure and dominance, and projects involving the
construction of an infrastructure must ensure open and non-discriminatory access
to the infrastructure and non-discriminatory pricing.
280 In the present case, as regards the positive effects, in recital 359 of the contested
decision, the Commission stated that the Fixed Link was aimed at promoting
mobility, further integration and cultural exchange of people living on both sides
of that link, and to improve the connection between the Nordic countries and
central Europe for passengers as well as road and railway freight. In that regard,
the Commission stated that expected benefits from the Fixed Link had been
recognised at European level by including that link in the list of TEN-T priority
55
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
projects. In addition, the Commission referred to the positive effects on certain
economic sectors in the region, such as gas stations, retail, restaurants, hotels,
amusement parks and railway and bus transport. The Commission also stated that
the Fixed Link would also enhance the accessibility to railway transport with the
possibility of there being a transfer of freight and passengers from road to rail.
281 As regards the negative effects, in recital 360 of the contested decision, the
Commission stated that the opening of the Fixed Link would have a negative
impact on ferry operators serving the Rødby and Puttgarden route, and on other
routes, and on the activities of the ports used by those ferries. In that regard, the
Commission considered that Femern’s power to influence the operation of the
ferry services was limited on the ground that the aid was limited to the financing
needed for the costs incurred during the phase relating to the planning and
construction of the Fixed Link, with the funding gap as the upper limit. Therefore,
the Commission considered that the main impact on the ferry operators’ services
is created by the public authorities’ decision to construct the Fixed Link,
providing an alternative to existing modes of transport, and that it is not for the
Commission to call into question the choice made by the public authorities.
282 In addition, in recitals 361 to 363 of the contested decision, the Commission
examined, in turn, the risk of overcapacity on the market, the risk of a dominant
position and the general impact on competition and the risk of market foreclosure.
283 After stating that it was not for the Commission to assess the effects of the public
authorities’ decision on the construction of the Fixed Link, after weighing up the
negative and positive effects, in recital 365 of the contested decision, the
Commission concluded that the aid measures in favour of Femern, as reduced
following the revised notification that followed the Opening Decision, had only a
limited effect on competition and trade that was offset by the positive effects in
terms of contribution to the objective of common European interest.
284 In the first place, as regards the argument of the applicants, FSS, ECSA and
Rederi Nordö-Link that the Commission failed to quantify the positive and
negative effects of the aid for the purposes of assessing the seriousness of the
distortion of competition, it should be noted that it is accepted that the
consideration of the positive and negative effects of aid may be succinct (see, to
that effect, judgment of 13 December 2018,
Scandlines Danmark and Scandlines
Deutschland
v
Commission,
T-630/15, not published, EU:T:2018:942,
paragraph 255), or inferred implicitly from the examination of the effects of the
aid on competition and trade where the negative effects of the aid are limited (see,
to that effect, judgment of 9 June 2016,
Magic Mountain Kletterhallen and Others
v
Commission,
T-162/13, not published, EU:T:2016:341, paragraph 110).
285 In addition, it must be noted that paragraphs 41 to 43 of the IPCEI
Communication merely set out principles for the purposes of the examination of
the weighing up of the positive and negative effects of the aid, but do not require
those effects to be quantified. Therefore, the Commission cannot be criticised for
56
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
not having assessed those positive and negative effects on the basis of quantitative
factors taking into account the size of the beneficiary of the aid, its market share
relative to its competitors and the size of the amount of aid granted.
286 Furthermore, as regards the decisions relied on by the applicants, Rederi Nordö-
Link, Trelleborg Hamn and DFA, in which, according to those parties, the
Commission carried out a detailed analysis of the distortion of competition for the
purposes of weighing up the positive and negative effects, those decisions are
manifestly irrelevant in the light of the case-law referred to in paragraph 134
above, especially since they concern texts other than those governing State aid
intended to promote the completion of important projects of common European
interest.
287 Accordingly, the Commission cannot be criticised for not having quantified the
positive and negative effects of the aid for the purposes of assessing the
seriousness of the distortion of competition.
288 In the second place, it is necessary to examine whether, as the applicants submit,
the Commission made a manifest error of assessment in finding, in recital 360 of
the contested decision, that Femern’s ability to undermine competition from
ferries was limited by the fact that the aid was capped at the funding gap.
289 It should be noted that, as regards the negative effects of the Fixed Link on
existing transport services and in particular on the activities of ferry service
operators, the Commission, in recital 360 of the contested decision, drew a
distinction between, on the one hand, the negative effects attributable to the public
authorities’ decision to construct the Fixed Link, which offers an alternative to the
existing modes of transport, and, on the other hand, the negative effects
attributable to the aid measures granted to Femern. According to the Commission,
when weighing up the positive and negative effects, it must confine itself to
examining the negative effects of the aid measures granted to that undertaking.
290 In that regard, it must be noted that it has already been held that, in the context of
the review of State aid, it is not for the Commission to call into question the public
authorities’ choice to decide on the construction of an infrastructure that will
provide an alternative to existing means of transport on the ground that such a
project provides a solution which, on the whole, has positive results, even if the
putting into service of that infrastructure would result in the disappearance of the
existing modes of transport (see, to that effect, judgment of 13 December 2018,
Scandlines Danmark and Scandlines Deutschland
v
Commission,
T-630/15, not
published, EU:T:2018:942, paragraph 256).
291 Therefore, the Commission was entitled to consider that it could limit its
examination to the negative effects of the aid measures granted to Femern.
292 As regards the negative effects of the grant of aid measures to Femern, the
Commission found that the financing granted to Femern covered the costs of
planning and constructing the Fixed Link up to the limit of the funding gap, that
57
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
the amount of the fees for use of the Fixed Link was regulated by the public
authorities and that the possibility for that undertaking to grant discounts was
limited by the need to ensure sufficient revenues to pay for the operating costs and
to repay the loans taken out to finance the planning and construction of the Fixed
Link. Therefore, the Commission considered that Femern’s power to influence the
operation of ferry services was limited and that the main negative effects resulted
from the public authorities’ decision to construct the Fixed Link.
293 As regards the applicants’ argument that, in essence, the capping of aid at the level
of the funding gap is irrelevant for the purpose of proving that the aid does not
unduly distort competition on the ground that it is a factor taken into consideration
at the stage of the examination of the proportionality of the aid, it must be noted
that the need for a weighing of the expected positive effects in terms of realisation
of the objectives set out in Article 107(3)(a) to (e) TFEU against the negative
effects of aid in terms of distortion of competition and the effect on trade between
Member States is no more than an expression of the principle of proportionality
and the principle that the exemptions set out in Article 107(3) TFEU must be
interpreted strictly (see, to that effect, judgment of 20 June 2019,
a&o hostel and
hotel Berlin
v
Commission,
T-578/17, not published, EU:T:2019:437,
paragraph 124).
294 Furthermore, since the principle of proportionality seeks to limit aid to the
minimum necessary so as to reduce distortions in the internal market, it must be
held that the Commission is entitled to use, at the stage of weighing up the
positive and negative effects of the aid measures, the findings made in the context
of the examination of the proportionality of the aid. In the present case, the
limitation of the aid amount to the funding gap of the investment project meant
that the financing granted to Femern was limited to 27.3% of the eligible costs.
Thus, where the examination of the proportionality of State aid and the
examination of the weighing up of positive and negative effects are intrinsically
linked, such a limitation of the aid amount is a relevant factor in finding that the
negative effects of the aid measures are limited.
295 As regards the applicants’ argument by which, in essence, they claim that Femern
could use the option which it has under Paragraph 42(3) of the 2015 Construction
Law to grant discounts in order to set prices below those charged by ferry
operators, it must be noted that that argument is purely hypothetical, particularly
since, as the Commission stated, Femern is required to generate sufficient
revenues not only to be able to pay its operating costs but also to repay the loans
taken out to finance the planning and construction of the Fixed Link. Thus, if any
discounts granted by Femern were to involve a significant reduction in its
revenues, that undertaking might not be in a position to repay the State loans and
the loans with a State guarantee within the periods laid down in recitals 349 and
351 of the contested decision.
296 In the third place, it is necessary to ascertain whether, as the applicants submit, the
Commission made manifest errors of assessment in the examination of certain
58
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
negative elements which, taken individually or together, are capable of offsetting
the positive effects of the aid.
297 First, as regards the argument of the applicants, FSS, DFA, ECSA and VDR that
the Commission incorrectly concluded that the aid would not have the effect of
increasing overcapacity on the market for crossing the Fehmarn Belt, it must be
noted that that argument is based on a misreading of the contested decision.
298 In recital 361 of the contested decision, the Commission merely referred to an
argument that ‘Scandlines et al. further argued that the Fixed Link would develop
much additional capacity to an already saturated market’ and merely observed that
‘the creation of an alternative to the existing services that is different from and
considered superior by the Danish authorities cannot be equated to adding
capacity to a saturated market’.
299 It cannot therefore be held that the Commission itself found that the market for
crossing the Fehmarn Belt is saturated.
300 Moreover, it must be noted that the applicants, FSS, ECSA, DFA and VDR have
not provided any evidence to substantiate the assertion that there is overcapacity
on the market. Although the applicants rely on an average rate of use of ferry
services of only 49%, they have not, however, adduced any probative evidence to
support that assertion. In that regard, it must be stated that the mere reference to
an identical assertion contained in observations submitted during the formal
investigation procedure, which is also not supported by any probative documents,
cannot constitute evidence.
301 In addition, as the Commission submits, it must be noted that neither the
applicants nor FSS, ECSA, DFA and VDR put forward any substantiated
arguments capable of calling into question the finding, in recital 361 of the
contested decision, that the creation of an alternative to the existing services that is
different from and considered superior, cannot be equated to adding capacity to a
saturated market. It must be stated that their line of argument is based on the
premiss, which is not supported by evidence, that there is overcapacity on the
market.
302 Accordingly, the applicants and those interveners have not demonstrated that the
Commission made a manifest error of assessment by finding that the Fixed Link
would not lead to overcapacity on the market for services offered for crossing the
Fehmarn Belt.
303 Second, it is necessary to ascertain whether, as the applicants claim, the
Commission made a manifest error of assessment by taking insufficient account of
the risk of a dominant position.
304 In the present case, in recital 362 of the contested decision, although the
Commission accepted that it could not be excluded that Femern would acquire a
dominant position on certain transport services on the Fehmarn Belt market, it
59
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
nevertheless stated that the existence of a dominant position was not in itself
contrary to EU law. In addition, after finding that Scandlines currently held a
monopoly on the route between Rødby and Puttgarden, it considered that, if there
were continued ferry services on that route, the Fixed Link would contribute to
breaking that monopoly, which would create a more competitive market.
305 It must be noted that paragraph 43 of the IPCEI Communication merely states that
the Commission will assess the risk of dominance, without providing details for
cases in which aid is granted for an infrastructure construction project. In addition,
it must be noted that, according to paragraph 41 of the IPCEI Communication, aid
may be declared compatible with Article 107(3)(b) TFEU where its negative
effects in terms of distortions of competition and impact on trade between
Member States are limited and outweighed by the positive effects in terms of
contribution to the objective of the common European interest.
306 Thus, contrary to what, in essence, the applicants claim, paragraph 43 of the
IPCEI Communication cannot be interpreted as meaning that aid which is capable
of contributing to the creation of a dominant position should systematically be
regarded as having negative effects which necessarily offset the positive effects of
an important project of common European interest, particularly since, in the
present case, the risk of a dominant position is limited to the local market for
transport services for crossing the Fehmarn Belt.
307 In that regard, it should be noted that neither the applicants nor the interveners in
support of their claims dispute the positive effects of the Fixed Link identified in
recital 359 of the contested decision. In that regard, the Commission found that
the positive effects of the Fixed Link were not limited to the beneficiary of the aid
or to the undertakings established in the Fehmarn Belt region, but extended more
widely within the European Union in that the Fixed Link would improve the
connection between the Nordic countries and central Europe for passengers and
for road and railway freight, as well as accessibility to railway transport, thus
contributing to the transfer of freight and passengers from road to rail. It follows
that, as is apparent from recital 281 of the contested decision, the Fixed Link
project, as an important project of common European interest, will contribute to
improving the functioning of the internal market and strengthening economic and
social cohesion.
308 In view of the fact that the positive effects of the Fixed Link are not limited to the
economic operators in one Member State, but benefit other economic operators in
the European Union more widely, the Commission was entitled, in the exercise of
its broad discretion, to take the view that the risk of a dominant position on a local
market for transport services was not capable of offsetting the positive effects of
the Fixed Link in terms of a contribution to the objective of common European
interest.
309 In addition, it is apparent from recital 362 of the contested decision that, on the
market for transport services for crossing the Fehmarn Belt, namely on the route
60
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
between Rødby and Puttgarden, the applicants currently hold a monopoly.
Therefore, the Commission was entitled to find, without making a manifest error
of assessment, that, if ferry services continued to operate on that route, the Fixed
Link would strengthen competition on that market.
310 Furthermore, while it is true that Scandlines does not hold a monopoly on a
geographic market extending beyond that of the route between Rødby and
Puttgarden, as the Commission rightly argues, there is also no risk that Femern
will hold a dominant position on a more extended geographic market.
311 Accordingly, the Commission did not make a manifest error of assessment in
finding that the risk of Femern holding a dominant position did not mean that that
negative effect of the aid in terms of distortion of competition offsets the positive
effects of the project in terms of contribution to the objective of common
European interest.
312 Third, it is necessary to ascertain whether the Commission made a manifest error
of assessment in not finding that there was a risk of market foreclosure.
313 It should be noted that, by their line of argument, the applicants, ECSA,
Trelleborg Hamn, Rederi Nordö Link and VDR do not dispute, as such, the
findings in recital 363 of the contested decision relating to the absence of a risk of
market foreclosure. In the present case, the Commission considered that there was
no risk of market foreclosure, including on the up- and downstream markets, on
the ground that the Fixed Link would be open to all users on an equal and non-
discriminatory basis. It also found that the pricing structure would be non-
discriminatory and in line with Directive 1999/62/EC of the European Parliament
and of the Council of 17 June 1999 on the charging of heavy goods vehicles for
the use of certain infrastructures (OJ 1999 L 187, p. 42) and with Directive
2012/34/EU of the European Parliament and of the Council of 21 November 2012
establishing a single European railway area (OJ 2012 L 343, p. 32).
314 By their line of argument, the applicants and those interveners complain that the
Commission, in essence, failed to take account of a risk of price dumping. In that
regard, it must be noted that that line of argument is essentially based on
arguments similar to those raised in the first sub-complaint of the second
complaint in the third part of the second plea, alleging a manifest error of
assessment in the assessment of the funding gap revenues (see paragraphs 216 to
235 above). The applicants and those interveners complain that the Commission
found that there was no risk of market foreclosure even though Femern’s prices
were lower than its costs.
315 It must be noted that the applicants, ECSA, Rederi Nordö Link, Trelleborg Hamn
and VDR have not explained why the authorisation of aid measures covering a
limited part of the planning and construction costs of an infrastructure project
would have the effect of foreclosing the market. In addition, as follows from
paragraph 224 above, it cannot be required that Femern’s revenues should be
61
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
established at a level that would cover all the planning, construction and operating
costs on the ground that that would mean that no aid could be granted to Femern
even though it is necessary for the completion of the project. In addition, as the
Commission rightly submits, since Femern is required to generate sufficient
revenue not only to cover its operating costs, but also to repay the debt taken on to
cover the planning and construction costs, the risk that that undertaking might
grant significant price discounts is necessarily limited.
316 As regards the applicants’ argument that Femern could use its dominant position
to lower prices below its costs in order to foreclose the market, it must be noted
that the amount of the fees for use of the Fixed Link is determined by the public
authorities and that Femern has only a certain amount of leeway to grant some
discounts. That undertaking is required to generate sufficient revenue not only to
be able to pay its operating costs, but also to repay the loans taken out to finance
the planning and construction of the Fixed Link. Therefore, if Femern were to
grant some discounts, it would nevertheless have to ensure that the level of
revenues remains sufficient to repay the State loans and the State guarantees
within the periods specified in recitals 349 and 351 of the contested decision.
317 Moreover, the applicants cannot argue that Femern could drastically reduce prices
in order to foreclose the market on the ground that, when the Danish authorities
granted State aid for the Øresund Belt fixed link, the operator of that link
significantly reduced the charges for road traffic. While it is true that the
applicants have adduced evidence of a reduction in the amount of those charges
compared with what was initially envisaged, they have not, however, adduced any
evidence to support the conclusion that the situation of the operator of the
Øresund Belt fixed link is comparable to that of Femern. In that regard, the
Commission stated that, unlike the aid granted to the operator responsible for the
Øresund Belt fixed link, in the present case the amount and duration of the
measures granted to Femern were strictly limited.
318 Accordingly, the line of argument alleging that the Commission made a manifest
error of assessment in finding that there was no risk of market foreclosure must be
rejected.
319 It follows from the foregoing considerations that the applicants and the interveners
in support of their claims have not demonstrated, first, that the Commission’s
findings that there was no risk of market saturation and no risk of market
foreclosure are vitiated by manifest errors of assessment and, second, that the
Commission made a manifest error of assessment in finding that the risk of a
dominant position did not offset the positive effects in terms of contribution to the
objective of common European interest.
320 Accordingly, the line of argument alleging that the Commission made manifest
errors of assessment in the examination of certain negative elements which, taken
individually or together, are capable of offsetting the positive effects in terms of
contribution to the objective of common European interest must be rejected.
62
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
321 In the fourth place, as regards the applicants’ line of argument by which, in
essence, it is alleged that the Commission failed to take account of the fact that the
access plans for Scandlines’ facilities in Puttgarden are downgraded, it should be
noted, first of all, that the evidence adduced by the applicants, on which there are
road layout modifications in the vicinity of Puttgarden, is not sufficiently precise
to determine that Femern is responsible for the construction of those modifications
to the roads. In that regard, as the Kingdom of Denmark has stated, it follows from
Article 5(2) of the Fehmarn Belt Treaty that, in principle, it is for the German
authorities to carry out the upgrading and financing of the hinterland connections
up to the Fixed Link.
322 Next, even if Femern were to carry out works for the construction of certain roads
in the territory of the Federal Republic of Germany, there is no evidence to
establish that that undertaking decided on the layout of those roads. Contrary to
what the applicants submit, it is not apparent from the contract concluded on
30 October 2009 between Femern and the Federal Republic of Germany
represented by the
Land
of Schleswig-Holstein that the German authorities
delegated to that undertaking the necessary powers to decide on the layout of
roads in the territory of the Federal Republic of Germany. It is apparent from
Article 2(1) of that contract that the sovereign powers of the State are not
transferred to Femern.
323 It follows that, since responsibility for ensuring access to the port of Puttgarden
lies with the German authorities, the Commission was fully entitled to consider
that it was not for the Commission, in the context of the review of State aid, to
assess whether road modifications would hinder access to the port of Puttgarden.
324 Furthermore, as regards the claim that Femern has used the aid to remove
Scandlines’ rail access to the port of Rødby, it must be noted that the evidence
provided is not precise enough to determine whether the removal of that access
concerns the construction of the Fixed Link as such or whether it concerns the
construction of the rail hinterland connections, which are the responsibility of
Banedanmark on behalf of Femern Landanlæg.
325 In the fifth place, as regards the applicants’ argument that the aid distorts
competitors’ investments on the ground that the Danish Minister for Transport
refused to support an application for financing under the CEF for a zero-emissions
ferry project, it must be noted that that decision not to support the applicants’
project was adopted by the Danish Government in the context of the
implementation of transport policy and is not imputable to Femern. It follows that
the Commission was entitled to conclude, in recital 360 of the contested decision,
that such a decision cannot be taken into account in the balancing assessment.
326 In the sixth place, as regards the line of argument, raised for the first time at the
hearing by NABU, that, in the balancing exercise, the Commission did not take
sufficient account of the environmental impact of the Fixed Link, that line of
argument must be rejected as inadmissible on the ground that the application does
63
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
not contain any complaint or argument calling into question the merits of the
findings made by the Commission in recitals 366 to 368 of the contested decision.
In any event, that line of argument cannot succeed. It is not supported by any
evidence and, moreover, taking into account environmental considerations is not
part of weighing up the positive and negative effects of the aid measure (see, by
analogy, judgment of 22 September 2020,
Austria
v
Commission,
C-594/18 P,
EU:C:2020:742, paragraphs 101 and 102). Moreover, although the Commission
found, in recitals 367 and 368 of the contested decision, that the Danish
authorities took account of the environmental impact of the Fixed Link, that that
impact was considered and mitigated and that the basis for the project was that it
should be prepared, constructed and operated so that harmful effects on nature and
the environment are prevented and so that considerable adverse impacts are
countered, NABU has not adduced any evidence capable of calling into question
those findings.
327 In the light of the foregoing considerations, the fourth part of the second plea must
be rejected in its entirety.
328 In the light of all of the foregoing considerations, the action must be dismissed.
III. Costs
329 Under Article 134(1) of the Rules of Procedure, the unsuccessful party is to be
ordered to pay the costs if they have been applied for in the successful party’s
pleadings. As the applicants have been unsuccessful, they must be ordered to pay
the costs, in accordance with the form of order sought by the Commission.
330 Under Article 138(1) of the Rules of Procedure, the Member States which
intervened in the proceedings are to bear their own costs. Accordingly, the
Kingdom of Denmark, which intervened in support of the form of order sought by
the Commission, must bear its own costs.
331 Under Article 138(3) of the Rules of Procedure, the Court may order an intervener
other than those referred to in paragraphs 1 and 2 of that article to bear its own
costs. In the present case, ECSA, DFA, NABU, VDR, Aktionsbündnis, FSS,
Rederi Nordö-Link and Trelleborg Hamn must bear their own costs.
On those grounds,
THE GENERAL COURT (First Chamber, Extended Composition)
hereby:
1.
Dismisses the action;
64
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
2838050_0066.png
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
2.
Orders Scandlines Danmark ApS and Scandlines Deutschland GmbH to
bear their own costs and to pay those incurred by the European
Commission;
Orders the Kingdom of Denmark, European Community Shipowners’
Associations (ECSA), Danish Ferry Association, Naturschutzbund
Deutschland eV (NABU), Verband Deutscher Reeder eV,
Aktionsbündnis gegen eine feste Fehmarnbeltquerung eV, Föreningen
Svensk Sjöfart (FSS), Rederi AB Nordö-Link and Trelleborg Hamn AB
to bear their own costs.
Spielmann
Brkan
3.
Papasavvas
Gâlea
Tóth
Delivered in open court in Luxembourg on 28 February 2024.
V. Di Bucci
M. van der Woude
Registrar
President
28 February 2024
65
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
J
UDGMENT OF
28. 2. 2024 – C
ASE
T-390/20
Table of contents
I.
A.
B.
C.
D.
E.
II.
Background to the dispute ............................................................................... 3
The Fehmarn Belt Fixed Link project.......................................................... 3
Events prior to the dispute ........................................................................... 5
Administrative procedure ............................................................................ 6
Contested decision ....................................................................................... 6
Forms of order sought .................................................................................. 7
Law .................................................................................................................. 7
A. The first plea in law, alleging that the Commission incorrectly classified
the measures at issue as one single ad hoc aid ..................................................... 7
B.
The second plea in law, alleging infringement of Article 107(3)(b) TFEU
……………………………………………………………………………15
1. The first part, alleging that the Commission incorrectly classified the
project as a project of common European interest......................................... 16
(a) Admissibility of the new complaint alleging breach of the principle
of the phasing out of environmentally harmful subsidies .......................... 16
(b) The third complaint, alleging that the project is not co-financed by
Femern ....................................................................................................... 17
(c) The first and second complaints, alleging that there is no positive
socioeconomic return ................................................................................. 18
2. The second part, alleging that the Commission was wrong to conclude
that the aid was necessary .............................................................................. 23
(a)
The first complaint, alleging that the aid had no incentive effect .... 23
(b) The second complaint, alleging that the Commission was wrong to
find that the counterfactual scenario consisted in the absence of an
alternative project ...................................................................................... 29
(c) The third complaint, challenging the periods used for the purposes of
calculating the IRR (necessity of the aid) and of calculating the funding
gap (proportionality of the aid) .................................................................. 33
3. The third part, alleging that the Commission was wrong to conclude that
the aid was proportionate ............................................................................... 40
(a)
(b)
The first complaint, challenging the temporal limitation of the aid . 40
The second complaint, challenging the funding gap ........................ 44
(1) The first sub-complaint, challenging the revenue ......................... 45
(2) The second sub-complaint, challenging the costs ......................... 48
(c)
The third complaint, challenging the aid amount ............................. 51
4. The fourth part, challenging the analysis of the prevention of undue
distortions of competition and the balancing test .......................................... 55
66
EUU, Alm.del - 2023-24 - Bilag 395: Notat om Femern Bælt-forbindelsen
S
CANDLINES
D
ANMARK AND
S
CANDLINES
D
EUTSCHLAND V
C
OMMISSION
III. Costs................................................................................................................. 64
67